Trial Operation and Testing

1.

Trial operation and testing.

1-1 Measure the supply voltage and make sure that it falls in the specified range.
1-2 Trial operation should be carried out in either cooling or heating mode.

For heat pump

1) In cooling mode, select the lowest programmable temperature; in heating mode, select the highest 

programmable temperature. 
Trial operation may be disabled in either mode depending on the room temperature.

2) After trial operation is complete, set the temperature to a normal level (78˚F to 82˚F (26˚C to 28˚C) in 

cooling mode, 68˚F to 75˚F (20˚C to 24˚C) in heating mode).

• For protection, the unit disables restart operation for 3 minutes after it is turned off.

For cooling only

Select the lowest programmable temperature.

1) Trial operation in cooling mode may be disabled depending on the room temperature. 
2) After trial operation is complete, set the temperature to a normal level (78˚F to 82˚F (26˚C to 28˚C)).
3) For protection, the system disables restart operation for 3 minutes after it is turned off. 

1-3 Carry out the test operation in accordance with the operation manual to ensure that all functions and 

parts, are working properly.

The air conditioner requires a small amount of power in its standby mode.  If the system is not to be used for 
some time after installation, shut off the circuit breaker to eliminate unnecessary power consumption.

If the circuit breaker trips to shut off the power to the air conditioner, the system will restore the original 
operation mode when the circuit breaker is opened again.

2.

Test items.

Incomplete cooling/heating function

No refrigerant gas leaks.

Draining line is properly installed.

Indoor and outdoor units are installed properly on 
solid bases.

Refrigerant gas and liquid pipes and indoor drain 
hose extension are thermally insulated.

Fall, vibration, noise

Water leakage

Water leakage

System is properly ground to earth.

Electrical leakage

Indoor unit properly receives remote controller 
commands.

Inoperative

Indoor or outdoor unit’s air intake or exhaust has 
clear path of air. 
Stop valves are opened.

Incomplete cooling/heating function

The specified wires are used for inter-unit wiring.

Inoperative or burn damage

Test items

Symptom

Check

Содержание RKS30

Страница 1: ... if it comes in contact with fire such as from a fan heater stove or cooking device Exposure to this gas could cause severe injury or death Do not ground units to water pipes telephone wires or lightning rods because incomplete grounding could cause a severe shock hazard resulting in severe injury or death and to gas pipes because a gas leak could result in an explosion which could lead to severe ...

Страница 2: ...ecified types of wires for electrical connections between the indoor and outdoor units Follow all state and local electrical codes Firmly clamp the inter unit wire so their terminals receive no external stresses Incomplete connections or clamping may cause terminal overheating fire or equipment damage After connecting all wiring be sure to shape the cables so that they do not put undue stress on t...

Страница 3: ... under the unit anything which must be kept away from moisture NOTE Cannot be installed hanging from ceiling or stacked Check the strength and level of the installation ground so that the unit will not cause any operating vibration or noise after installed In accordance with the foundation drawing fix the unit securely by means of the foundation bolts Prepare four sets of 1 2 inch M12 foundation b...

Страница 4: ...mm of work space below the ceiling surface 9 7 8 250mm from wall Allow space for piping and electrical servicing Right side plate 13 5 8 345mm Clamping material Insulation tube Bottom frame Tape Also insulate the connection on the outdoor unit Use tape or insulating material on all connections to prevent air from getting in between the copper piping and the insulation tube Be sure to do this if th...

Страница 5: ...ps into their matching drain hole Drain socket A into drain hole I and drain caps B into drain hole II and III After insertion turn them about 40 clockwise Be sure not to insert them into wrong drain holes or there causes water leakage View from bottom 3 Connect vinyl hose on the market internal diameter of 1 inch 25mm to drain socket A If the hose is too long and hangs down fix it carefully to pr...

Страница 6: ...9 7N m Valve cap tightening torque Service port cap tightening torque 7 9 10 8ft lbf 10 8 14 7N m CAUTION 1 Use the flare nut fixed to the main unit To prevent cracking of the flare nut by aged deterioration 2 To prevent gas leakage apply refrigeration oil only to the inner surface of the flare Use refrigeration oil for R410A 3 Use torque wrenches when tightening the flare nuts to prevent damage t...

Страница 7: ...mage the vacuum pump or the unit 1 Connect projection side of charging hose which comes from gauge manifold to gas stop valve s service port 2 Fully open gauge manifold s low pressure valve Lo and completely close its high pressure valve Hi High pressure valve subsequently requires no operation 3 Do vacuum pumping and make sure that the compound pressure gauge reads 29 9inHg 0 1MPa 1 4 Close gauge...

Страница 8: ...sure to pump down when relocating or disposing of the unit 1 Remove the valve cap from liquid stop valve and gas stop valve 2 Carry out forced cooling operation 3 After 5 to 10 minutes close the liquid stop valve with a hexagonal wrench 4 After 2 to 3 minutes close the gas stop valve and stop forced cooling operation Forced cooling operation 1 Press the Forced Operation switch SW1 to begin forced ...

Страница 9: ...er harmonics This unit uses an inverter which means that it must be used an earth leak detector capable handling harmonics in order to prevent malfunctioning of the earth leak detector itself 4 Use an all pole disconnection type breaker with at least 1 8 inch 3mm between the contact point gaps 5 When carrying out wiring connection take care not to pull at the conduit 6 Do not connect the power wir...

Страница 10: ...voidable reasons be sure to observe the following instruction Place the round crimp style terminals on the wires up to the covered part and secure in place Ground terminal installation Use the following method when installing the round crimp style terminal CAUTION 1 Stranded wire Round crimp style terminal 1 2 3 1 2 3 Safety breaker 20A Earth leakage circuit breaker Earth Firmly fix the wires with...

Страница 11: ...door temperature rises the operation will start again 1 If the outdoor unit is installed where the heat exchanger of the unit is exposed to direct wind provide a windbreak wall 2 Intermittent noises may be produced by the indoor unit due to the outdoor fan turning on and off when using facility settings 3 Do not place humidifiers or other items which might raise the humidity in rooms where facilit...

Страница 12: ...ter it is turned off 1 3 Carry out the test operation in accordance with the operation manual to ensure that all functions and parts are working properly The air conditioner requires a small amount of power in its standby mode If the system is not to be used for some time after installation shut off the circuit breaker to eliminate unnecessary power consumption If the circuit breaker trips to shut...

Страница 13: ...3P235796 1F M08B133E ...

Отзывы: