9. Locate and install the fulcrum used in the leveling
):
a. Wipe the bottom of the louver door where the
fulcrum will be located so that the duct tape will
stick to it.
b. b Pre-apply duct tape to the top surface of the
bottom portion of the fulcrum, extending it about
one inch beyond the edges on three sides.
c. With the alignment plate taped to the vane and the
vane in the zero airflow position, locate the fulcrum
parallel to and against the alignment plate.
d. Once the fulcrum is in position, press the duct tape
extensions down to hold the fulcrum in place.
e. Remove the alignment plate after installing the
fulcrum.
NOTE:
The zero airflow position is when the vane is
swung away from the back wall and gently resting
against its stop.
10. Close and latch the louvered intake door.
11. Remove the cover from the access opening in the bottom
blade of the outdoor air intake louver (see
).
12. Verify that the unit fans are off and that the outdoor air
dampers are closed. If there is a wind, cover the outdoor
air louvers with poly film, cardboard, or other suitable
material to prevent adverse readings due to wind.
13. Rest the leveling weight assembly on the fulcrum, as
shown in
a. Its bottom two thumbscrews rest on the top edge
of the fulcrum.
b. Its top thumbscrew rests against the vertical
alignment mark on the vane.
NOTE:
The alignment mark is located 0.50 inch in from the
bend on the outer edge of the vane. It intersects with
a hole located one inch up from the bottom outer
edge of the vane.
14. Set up the leveling test as follows:
a. While holding the weight so it stays on the fulcrum,
manually rotate the vane to the wide-open position,
manually return it to the zero CFM position, and
gently release the vane.
b. Locate the leveling weight assembly so its contact
point is against the vertical mark on the vane.
c. While the weight assembly teeters on the fulcrum,
gently rap the base frame to slightly vibrate the
assembly and encourage the vane to seek its
equilibrium point.
15. Read the current
LH Lvl Pos=
(or
RH Lvl Pos=
)
parameter in the Min OA Setup menu on the keypad/
display. These parameters vary from 20% to 80%
depending on the position of the DesignFlow vane
16. If the value indicated by the
LH Lvl Pos=
(or
RH Lvl
Pos=
) parameter is not within the range of
22 .56%
to
23 .02%
(
22 .79% is ideal
), adjust the level of the
DesignFlow unit using the procedure described in
“Making Level Adjustments” below.
17. When the
LH Lvl Pos=
(or
RH Lvl Pos=
) value is in range,
remove the fulcrum and leveling weight assembly and
replace the access opening cover in the louvered door.
Figure 85: Tape Fulcrum Alignment Plate to Vane
Figure 86: Place Leveling Weight on Fulcrum
Vane
Duct tape
This edge flush
with this side of vane
These edges flush
with bottom of vane
Fulcrum alignment plate
Fulcrum
Duct tape
Содержание RDT
Страница 60: ...IM 893 10 ROOFPAK SINGLEZONE UNITS 60 www DaikinApplied com Wiring Diagrams Figure 64 VFD Control SAF and RAF...
Страница 61: ...Wiring Diagrams www DaikinApplied com 61 IM 893 10 ROOFPAK SINGLEZONE UNITS Figure 65 VAV Control Inputs...
Страница 65: ...Wiring Diagrams www DaikinApplied com 65 IM 893 10 ROOFPAK SINGLEZONE UNITS Figure 67 Electric Heat Control...