Installation

www.DaikinApplied.com 

IM 1272 • OPTILINE VERTICAL FAN COILS

Installation

Installation of Units with Risers Attached

 WARNING

Use solder to connect the risers. Do not use Silfos (brazing) as this will 

cause the pipe to overheat and the insulation to be damaged. 

 NOTICE

Daikin does not advise on the location or method of anchoring as this is 

the responsibility of the engineering company retained to design the riser 

system.

 CAUTION

Sharp edges and coil surfaces are a potential injury hazard. Avoid contact 

with them.

A rectangular opening is made in the floor slab, usually 

sleeved before pouring the floor. Refer to the catalog or 

submittals for sizes.
Rotate the unit from the horizontal position to vertical so that 

the bottom end of the risers insert into the expanded end of the 

risers on the unit below. 2" is allowed in the riser length for the 

depth of the insertion. Shim the unit plumb.
Before making the solder joint, ensure that the run outs 

from the supply and return risers are centered in the slots in 

the cabinet. If this is not done there is considerable risk of 

distorting the run out when the hot water riser expands causing 

the run out to contact the edge of the slot in the sheet metal 

potentially causing failures or leaks. Also ensure that the 

condensate riser stub out is at 90° to the cabinet so that the 

drain hose is not kinked.
Connect the risers by soldering (not brazing) using 95/5 

solder. An additional cap of 50/50 solder can be added for 

extra strength.
Ensure that the horizontal run-out from each riser is centered 

in the slot in the cabinet and that the run-out from the riser 

is at 90º as it enters the cabinet, prior to soldering the risers. 

Anchoring the risers to the floor slabs is the responsibility 

of the contractor. Shim the unit plumb. It is not necessary to 

use a pad under the unit. Fire stopping the floor opening and 

making good the riser insulation at the floor opening is the 

responsibility of the contractor. Check that the drain hose is 

not kinked before soldering the condensate riser. If the risers 

incorporate expansion compensation loops, remove the 

support brackets after anchoring the risers.

The fan coil unit has unions at the shut off valves. These 

fittings must be checked prior to pressure testing the system by 

the contractor as part of the installation procedure. Mechanical 

fittings can loosen during transportation and handling. If 

contractor /installer deem it necessary to tighten mechanical 

fittings Daikin does not assume any responsibility for this 

procedure. It is stressed that the component manufacturer’s 

recommended procedures be strictly followed.
The coil is pressure tested hydrostatically at the factory using 

a propylene glycol solution. Trace amounts of this solution are 

allowed to remain in the coil to ensure that the coil does not 

freeze during transportation. After testing on site with water the 

fan coil unit must not be exposed to freezing temperatures.
Riser anchoring is required for two purposes. The risers are 

anchored to the floor slab at one or more points in the height 

of the building so that they do not slip down under gravity. 

The second reason is to spread the expansion in opposite 

directions from the anchor point. Typically risers will be 

anchored at the midpoint of the height of the building. If there 

are riser expansion loops included in the risers inside the unit, 

the anchor point will be at the midpoint between two sets of 

loops. For example in a 16 story building there will be a loop 

on the hot water riser on floor 8 and anchors at floors 4 and 12. 

After anchoring, the risers are in effect attached to the building 

structure so it does not matter if the plastic straps holding the 

risers to the unit break off after installation. 

•  Complete the riser insulation at the solder joint is the 

responsibility of the contractor

• 

Fire stop the floor opening in accordance with code

Flushing and Testing

The fan coil is normally equipped with ball type shut off valves.  

The unit is shipped with the ball valves open to the coil.

After checking mechanical fittings inside the unit for tightness, 

it is recommended that the units on each riser stack are 

pressure tested using compressed air or nitrogen.

• 

Close the ball valves and flush the riser system

•  Open the supply side ball valve and bleed air from the 

coils. The coil has a manual air vent for this purpose. 

The top of each riser should also have an air vent (not 

provided by the factory)

•  Test the units and risers hydrostatically. Open the return 

side ball valve after testing

•  Check that the strainer mesh is not choked, if there are 

strainers included with the unit

Содержание OptiLine FSG

Страница 1: ...Installation Operation and Maintenance IM 1272 Group Fan Coils Part Number 910243712 Date July 2018 OptiLine Vertical Stack Fan Coil Model FSG...

Страница 2: ...Receiving Inspection 4 Installation 5 Installation of Units with Risers Attached 5 Maintenance 7 Operating Instructions 8 Standard Thermostat Digital Programmable Thermostat 8 Adjusting the Maximum CF...

Страница 3: ...Provide adequate combustion and ventilation air to the unit space as specified in the combustion and ventilation air section of these instructions WARNING Install this unit only in a location and pos...

Страница 4: ...rocedure It is stressed that the component manufacturer s recommended procedures be strictly followed Thermostats and other accessories which have been shipped separately should be inspected for trans...

Страница 5: ...fittings must be checked prior to pressure testing the system by the contractor as part of the installation procedure Mechanical fittings can loosen during transportation and handling If contractor in...

Страница 6: ...ian must carry out the work The junction box is located behind the fan motor shield Electrical power to the unit should be disconnected by opening the remote disconnect device prior to removing the fa...

Страница 7: ...the grille panel Grasp the bottom edge of the door and sharply pull the door forwards Lift the door to the horizontal position The filter is now accessible and is removed by sliding it upwards out of...

Страница 8: ...al to a 0 10VDC Adjusting the Maximum CFM WARNING If the maximum CFM is adjusted to a value above the design airflow excessive air noise could occur The maximum CFM is factory set to the closest nomin...

Страница 9: ...e than 100 F the A2 aquastat energizes the control valve If the water drops below 75 F the aquastat de energizes the control valve and energizes the electric heat relay The A2 aquatat has black yellow...

Страница 10: ...d there is supply voltage to the fan motor replace the fan assembly If the system is change over or has auxiliary electric there check the voltage at the aquastats If no voltage is present at BLK or Y...

Страница 11: ...r free and proper fan rotation Record electrical supply voltage and amperage Check all wiring for secure connections Close all unit isolation valves Flush water systems Open all isolation valves after...

Страница 12: ...1 2 TB1 1 2 5 6 YEL BLK QC3 5 8 2 1 QC3 BLK BLK BLK BLK BLK N L L2 L1 MAX FUSE 15 AMPS SYM Description DISC SWITCH 1 POLE 120 277V 30A XMR1 TRANSFORMER 120 208 240 277 TO 24V 40VA CLASS 2 F1 FUSE 250V...

Страница 13: ...12 AMPS BLK BLK BLK 2 1 BLK BLK L2 L1 TB1 1 2 5 6 YEL BLK QC3 5 8 2 1 QC3 L1 L2 SYM Description DISC SWITCH 2 POLE 120 277V 30A XMR1 TRANSFORMER 120 208 240 277 TO 24V 40VA CLASS 2 M1 MOTOR 208V 1 10...

Страница 14: ...LD 22AWG 2 COND SHIELD AC DC SHIELDED WIRE GND L N QC3 QC3 2 M1 L2 GND SYM Description DISC SWITCH 1 POLE 120 277V 15A XMR1 TRANSFORMER 120 208 240 277 TO 24V 40VA CLASS 2 M1 EBM MOTOR 120V 1 5 HP CVA...

Страница 15: ...WIRE N GND NC GND 1 8 AMPS FAN MOTOR QC3 M1 2 QC3 SYM Description DISC SWITCH 1 POLE 120 277V 15A XMR1 TRANSFORMER 120 208 240 277 TO 24V 40VA CLASS 2 M1 MOTOR 208 277 2 3 HP QC3 9 PIN QUICK CONNECT...

Страница 16: ...rn ON OFF thermostat 7 Set point icons Display set point temperature while it is flashing 8 Fan icons Indicate Fan status 9 Flake icon Indicate working in Cooling mode 10 Hot spring icon Indicate work...

Страница 17: ...uit of the controller Mounting front cover Lock front cover on the backplate by tightening the cover screw underneath with Philip screwdriver Wiring Example 1 All wires must be inserted above the reta...

Страница 18: ...cription Remarks 1 Normal Display Display current room or set point temperature and current time day Setting SP parameter in engineer table to choose current room or set point temperature 2 Temperatur...

Страница 19: ...d com 19 IM 1272 OPTILINE VERTICAL FAN COILS Figure 10 User Mode Operation Sequence Figure 11 Overview for the Settings of Clock and Programmable Schedules MODE Press MODE FAN or POWER button to escap...

Страница 20: ...IM 1272 OPTILINE VERTICAL FAN COILS 20 www DaikinApplied com Addendum Figure 12 Detailed State Diagram for Clock Setting...

Страница 21: ...13 Detailed State Diagram for Schedule Setting Press Mode button to select day shows steadily deselect day flash Press MODE button to toggle Cooling Heating Set points Press MODE button to toggle Cool...

Страница 22: ...0 8 00 8 00 8 00 8 00 60 F 60 F 60 F 60 F 60 F 60 F 60 F Sch 3 MODE 18 00 18 00 18 00 18 00 18 00 18 00 18 00 70 F 70 F 70 F 70 F 70 F 70 F 70 F Sch 4 MODE 22 00 22 00 22 00 22 00 22 00 22 00 22 00 60...

Страница 23: ...LS Control Actions ON OFF Valve Controls When Cooling or Heating is on a Running Gear MODE icon will be shown on the LCD Figure 14 Cooling and Heating Control Auto Changeover Dead band Option 0 Figure...

Страница 24: ...o be ESIC ESIH refer to Engineer table for details When the contact is deactivated Open Room will be back to be occupied it will set the set point values back to normal 3 The icon MODE MODE MODE or MO...

Страница 25: ...ter into engineer mode 2 Press UP or DOWN button to rotate the menu item and press MODE button to enter into the item 3 Press UP or DOWN button to change the setting and press MODE button to confirm t...

Страница 26: ...0 10 0 10 0 0 0 18 0 18 0 0 1 C F E12 Pb Proportional Band or Stage Width 2 0 0 10 0 3 6 0 18 0 0 1 C F E13 LOC Bit Definition Bit 0 Mode Button 1 Down Buttons 2 Up Button 3 Fan Button 4 Power Button...

Страница 27: ...F Type Step Default Range Default Range E21 dirH Heating Valve N C N O Setting 1 0 1 0 0 1 0 N O 1 N C E22 dbOP Dead band Options 1 0 1 1 0 1 0 DB is aligned to Cooling SP 1 SP is in the middle of DB...

Страница 28: ...t to its standard terms and conditions of sale including Limited Product Warranty Consult your local Daikin Applied Representative for warranty details To find your local Daikin Applied Representative...

Отзывы: