background image

8 Commissioning

Installation manual

18

EKHWET90~120BAV3

R32 Split series – Domestic hot water tank

4P680074-1 – 2021.11

8

Commissioning

NOTICE

General 

commissioning 

checklist.

 

Next 

to 

the

commissioning  instructions  in  this  chapter,  a  general
commissioning  checklist  is  also  available  on  the  Daikin
Business Portal (authentication required).

The  general  commissioning  checklist  is  complementary  to
the  instructions  in  this  chapter  and  can  be  used  as  a
guideline and reporting template during the commissioning
and hand-over to the user.

NOTICE

ALWAYS operate the unit with thermistors and/or pressure
sensors/switches. If NOT, burning of the compressor might
be the result.

INFORMATION

Protective  functions  –  "Installer-on-site  mode"

.  The

software  is  equipped  with  protective  functions,  such  as
tank  disinfection.  The  unit  automatically  runs  these
functions when necessary.

During  installation  or  service  this  behaviour  is  undesired.
Therefore, the protective functions can be disabled:

At  first  power-on:

  The  protective  functions  are

disabled  by  default.  After  36  hours  they  will  be
automatically enabled.

Afterwards:

  An  installer  can  manually  disable  the

protective  functions  by  setting  [9.G]: 

Disable

protections

=

Yes

.  After  his  work  is  done,  he  can

enable  the  protective  functions  by  setting  [9.G]:

Disable protections

=

No

.

Also see 

"Protective functions"

 [

4

 14].

8.1

Checklist before commissioning

1

After the installation of the unit, check the items listed below.

2

Close the unit.

3

Power up the unit.

You  read  the  complete  installation  instructions,  as
described in the 

installer reference guide

.

The 

indoor unit

 is properly mounted.

The 

outdoor unit

 is properly mounted.

The following 

field wiring

 has been carried out according

to this document and the applicable legislation:

▪ Between the local supply panel and the outdoor unit

▪ Between indoor unit and outdoor unit

▪ Between the local supply panel and the indoor unit

The  system  is  properly 

earthed

  and  the  earth  terminals

are tightened.

The 

fuses

  or  locally  installed  protection  devices  are

installed according to this document, and have NOT been
bypassed.

The 

power  supply  voltage

  matches  the  voltage  on  the

identification label of the unit.

There  are  NO 

loose  connections

  or  damaged  electrical

components in the switch box.

There  are  NO 

damaged  components

  or 

squeezed

pipes

 on the inside of the indoor and outdoor units.

Booster  heater  circuit  breaker

  F2B  (field  supply)  is

turned ON.

There are NO 

refrigerant leaks

.

The 

refrigerant  pipes

  (gas  and  liquid)  are  thermally

insulated.

The  correct  pipe  size  is  installed  and  the 

pipes

  are

properly insulated.

There is NO 

water leak

 inside the indoor unit.

The 

stop  valves

  (gas  and  liquid)  on  the  outdoor  and

indoor units are fully open.

The 

domestic hot water tank

 is filled completely.

8.2

Checklist during commissioning

To perform a 

test run

.

To perform an 

actuator test run

.

8.2.1

To perform an operation test run

Conditions: 

Make  sure  all  operation  is  disabled.  Go  to  [C]:

Operation

 and turn off 

Tank

 operation.

1

Set the user permission level to 

Installer

. See 

"To

change the user permission level"

 [

4

 13].

2

Go to [A.1]: 

Commissioning

 > 

Operation test

run

.

3

Select the 

Tank

..

4

Select 

OK

 to confirm.

Result: 

The test run starts. It stops automatically

when ready (±30 min).

To stop the test run manually:

1

In the menu, go to 

Stop test run

.

2

Select 

OK

 to confirm.

INFORMATION

If  the  outdoor  temperature  is  outside  the  range  of
operation,  the  unit  may  NOT  operate  or  may  NOT  deliver
the required capacity.

To monitor tank temperatures

During test run, the correct operation of the unit can be checked by
monitoring its tank temperature (domestic hot water mode).

To monitor the temperatures:

1

In the menu, go to 

Sensors

.

2

Select the temperature information.

8.2.2

To perform an actuator test run

Conditions: 

Make  sure  all  operation  is  disabled.  Go  to  [C]:

Operation

 and turn off 

Tank

 operation.

Purpose

Perform an actuator test run to confirm the operation of the different
actuators.  For  example,  when  you  select 

Booster  heater

,  a  test

run of the booster heater will start.

1

Set the user permission level to Installer. See 

"To

change the user permission level"

 [

4

 13].

2

Go to [A.2]: 

Commissioning

 > 

Actuator test run

.

3

Select 

Booster heater

.

Содержание EKHWET90BAV3

Страница 1: ...Installation manual R32 Split series Domestic hot water tank English Installation manual R32 Split series Domestic hot water tank EKHWET90BAV3 EKHWET120BAV3 https daikintechnicaldatahub eu...

Страница 2: ...trukcij atbilst d m direkt v m vai regul m ja vien ie izstr d jumi tiek lietoti saska ar m su instrukcij m s v zhode s nasleduj cou imi smernicou ami alebo predpisom mi za predpokladu e sa v robky pou...

Страница 3: ...or test run 18 9 Hand over to the user 19 10 Technical data 20 10 1 Piping diagram Indoor unit 20 10 2 Wiring diagram Indoor unit 21 1 About this document Target audience Authorised installers Documen...

Страница 4: ...ng the indoor unit see 4 3 Mounting the indoor unit 410 WARNING Fixing method of the indoor unit MUST be in accordance with the instructions from this manual See 4 3 Mounting the indoor unit 410 Pipin...

Страница 5: ...g ambient temperatures Domestic hot water production 5 35 C Mind the following spacing installation guidelines 300 300 300 300 400 mm 300 300 Additionally to the spacing guidelines Because the total r...

Страница 6: ...ease height From floor to 100 mm below top of the unit N A Not applicable Minimum floor area Release height The minimum floor area requirements depend on the release height of the refrigerant in case...

Страница 7: ...d Must be 50 of Anv min minimum bottom opening area Must be 1 5 m from the floor A B Anv Anv min Min 50 of Anv min Calculate the total floor area Atotal AroomA AroomB See table 4 Look up the minimum b...

Страница 8: ...or area m 2 00 4 00 6 00 8 00 10 00 12 00 14 00 2 2 4 88 2 49 1 70 1 47 2 3 5 10 2 60 1 77 1 53 1 38 2 4 5 32 2 71 1 84 1 59 1 43 2 5 5 53 2 82 1 91 1 65 1 49 1 37 2 6 5 75 2 93 1 99 1 71 1 54 1 42 Ta...

Страница 9: ...a as specified in the table below 50 of the required opening area Anv min must be 200 mm from the floor of the unoccupied room The bottom of the opening must be 100 mm from the floor of the unoccupied...

Страница 10: ...ce when connecting the field piping and make sure the piping is aligned properly Deformation of the piping can cause malfunctioning of the unit For information related with piping length diameter conn...

Страница 11: ...the indoor unit a b a DHW hot water OUT screw connection b DHW cold water IN screw connection NOTICE A pressure relief valve field supply with an opening pressure of maximum 7 bar 0 7 MPa must be inst...

Страница 12: ...heater power supply Booster heater cable Wires 2 GND 1 5 mm 9 4 Booster heater WARNING The booster heater MUST have a dedicated power supply and MUST be protected by the safety devices required by th...

Страница 13: ...tings see 7 1 1 To access the most used commands 413 Afterwards If necessary you can make changes to the configuration in the menu structure or the overview settings INFORMATION When the configuration...

Страница 14: ...rotective functions The unit is equipped with the following protective function Tank disinfection 2 01 The unit automatically runs the protective function when necessary During installation or service...

Страница 15: ...ue When you later want to change the storage setpoint you only have to do it in one place The tank will heat up until the storage comfort temperature has been reached It is the higher desired temperat...

Страница 16: ...fine the weather dependent curve by its slope and offset Change the slope to differently increase or decrease the target temperature of the tank for different ambient temperatures For example if tank...

Страница 17: ...Cold Hot You feel Fine tune with slope and offset At regular outdoor temperatures At cold outdoor temperatures Slope Offset Hot OK Hot Cold Hot Hot See 7 3 3 Slope offset curve 416 To fine tune the w...

Страница 18: ...ly installed protection devices are installed according to this document and have NOT been bypassed The power supply voltage matches the voltage on the identification label of the unit There are NO lo...

Страница 19: ...inished and the unit operates properly please make sure the following is clear for the user Fill in the installer setting table in the operation manual with the actual settings Make sure that the user...

Страница 20: ...aikin website publicly accessible The full set of latest technical data is available on the Daikin Business Portal authentication required 10 1 Piping diagram Indoor unit R5T a1 c a2 R3T b1 b2 3D13820...

Страница 21: ...h box Multi DHW Tank switch box Multi domestic hot water tank switch box Indoor Indoor Outdoor Outdoor SWB Switch box 2 Legend 2 Legend A1P Main PCB F2B Overcurrent fuse booster heater FU1 A1P fuse 5...

Страница 22: ...wiring Power supply OUTDOOR UNIT X1M 1 2 3 earth 4 core X2M 1 2 3 earth INDOOR UNIT 1 1 booster heater power supply 1 2 kW 230 V earth STANDARD PART X1M L N earth Only for normal power supply installa...

Страница 23: ......

Страница 24: ...4P680074 1 2021 11 Copyright 2021 Daikin 4P680074 1 0000000N Verantwortung f r Energie und Umwelt...

Отзывы: