Louver Installation With Typical
Unit Configurations
Unit Configuration Type AL
Figure 9: The 16-5/8" (422mm) Deep Unit with Open Pipe
Tunnel and Standard Louver Location
Louver
Floor Line
Piping
Important:
Gasket sealing surface
is required.
Sealed Cement
Mortar; Pitch Away
From Unit
Lintel
(By Others)
1"
(25mm)
Figure 10:
16-5/8″ (422mm) Deep Unit with Open Pipe
Tunnel & High Louver Application with Chased Wall
Louver
Not Less Than
3" (76mm)
Not More Than
21" (533mm)
Sealed Cement
Mortar; Pitch Away
From Unit Provide
Drainage
Piping
Floor Line
1"
(25mm)
Important: Gasket sealing surface
is required.
Lintel
(By Others)
Accumulated moisture can cause property damage if not properly
drained. Installing contractor must provide such drainage.
CAUTION
Figure 11: Above Floor Level Outdoor Air Intake Using
Arrangement AV or AL With Accessory Closed Pipe Tunnel
Piping
Floor Line
Lintel (By Others)
Intake Louver
Not Less Than 3"
Not More Than 28"
Insulated Closure
Plate Accessory
Provide
Drainage
Important: Gasket sealing
surface is required.
1" (25mm)
Sealed Cement Mortar;
Pitch Away From Unit
Figure 12: Floor Level Outdoor Air Intake With Window
Below Unit Top Using Arrangement AL And 9″ “Finished”
(Painted) Accessory (Uninsulated) Closed Pipe Tunnel
Lintel (By Others)
Intake Louver
Important: Gasket sealing surface is
required.
Sash
Piping
Painted Insulated Closure Plate Accessory
Floor Line
Sealed Cement
Mortar; Pitch Away
From Unit
1"
(25mm)