11
|
Commissioning
Installer reference guide
237
ERGA04~08E + 23E
Daikin Altherma 3 R F
4P629090-1C – 2022.08
▪
Heating
▪
Cooling (if applicable)
▪
Tank
To perform an operation test run
Conditions:
Make sure all operation is disabled. Go to [C]:
Operation
and turn off
Space heating/cooling
and
Tank
operation.
1
Set the user permission level to
Installer
. See
139].
—
2
Go to [A.1]:
Commissioning
>
Operation test run
.
3
Select a test from the list.
Example:
Heating
.
4
Select
OK
to confirm.
Result:
The test run starts. It stops automatically when ready
(±30 min).
To stop the test run manually:
—
1
In the menu, go to
Stop test run
.
2
Select
OK
to confirm.
INFORMATION
If the outdoor temperature is outside the range of operation, the unit may NOT
operate or may NOT deliver the required capacity.
To monitor leaving water and tank temperatures
During test run, the correct operation of the unit can be checked by monitoring its
leaving water temperature (heating/cooling mode) and tank temperature
(domestic hot water mode).
To monitor the temperatures:
1
In the menu, go to
Sensors
.
2
Select the temperature information.
11.4.4 Actuator test run
Purpose
Perform an actuator test run to confirm the operation of the different actuators.
For example, when you select
Pump
, a test run of the pump will start.
To perform an actuator test run
Conditions:
Make sure all operation is disabled. Go to [C]:
Operation
and turn off
Space heating/cooling
and
Tank
operation.
1
Set the user permission level to Installer. See
139].
—
2
Go to [A.2]:
Commissioning
>
Actuator test run
.
3
Select a test from the list.
Example:
Pump
.
Содержание Altherma ERGA04E V3 Series
Страница 293: ...11 11...
Страница 294: ......
Страница 295: ......
Страница 296: ...4P629090 1C 2022 08 Copyright 2020 Daikin Verantwortung f r Energie und Umwelt...