7 Installation
Installer reference guide
38
ERLQ004~008CA + EHVH/X04+08S18+26CB
Daikin Altherma – Low temperature split
4P384973-1D – 2018.07
7.7.4
To determine the complete recharge
amount
INFORMATION
If a complete recharge is necessary, the total refrigerant
charge is: the factory refrigerant charge (see unit name
plate) + the determined additional amount.
7.7.5
To charge additional refrigerant
WARNING
▪ Only use R410A as refrigerant. Other substances may
cause explosions and accidents.
▪ R410A contains fluorinated greenhouse gases. Its
global warming potential (GWP) value is 2087.5. Do
NOT vent these gases into the atmosphere.
▪ When charging refrigerant, always use protective
gloves and safety glasses.
CAUTION
To avoid compressor breakdown, do NOT charge more
than the specified amount of refrigerant.
Prerequisite:
Before charging refrigerant, make sure the refrigerant
piping is connected and checked (leak test and vacuum drying).
1
Connect the refrigerant cylinder to the service port.
2
Charge the additional refrigerant amount.
3
Open the gas stop valve.
If pump down is needed in case of dismantling or relocating the
system, see
"13.2 To pump down" on page 84
for more details.
7.7.6
To fix the fluorinated greenhouse gases
label
1
Fill in the label as follows:
b
Contains fluorinated greenhouse gases
2
1
1
1
2
2
kg
tCO
2
eq
GWP × kg
1000
=
=
+
kg
=
kg
=
GWP: XXX
RXXX
a
f
c
d
e
a
If a multilingual fluorinated greenhouse gases label is
delivered with the unit (see accessories), peel off the
applicable language and stick it on top of
a
.
b
Factory refrigerant charge: see unit name plate
c
Additional refrigerant amount charged
d
Total refrigerant charge
e
Greenhouse gas emissions
of the total refrigerant charge
expressed as tonnes CO
2
equivalent
f
GWP = Global warming potential
NOTICE
In Europe, the
greenhouse gas emissions
of the total
refrigerant charge in the system (expressed as tonnes CO
2
equivalent) is used to determine the maintenance intervals.
Follow the applicable legislation.
Formula to calculate the greenhouse gas emissions:
GWP value of the refrigerant × Total refrigerant charge [in
kg] / 1000
2
Fix the label on the inside of the outdoor unit near the gas and
liquid stop valves.
7.8
Connecting the water piping
7.8.1
About connecting the water piping
Before connecting the water piping
Make sure the outdoor and indoor unit are mounted.
Typical workflow
Connecting the water piping typically consists of the following
stages:
1
Connecting the water piping to the indoor unit.
2
Connecting the recirculation piping.
3
Connecting the pressure relief valve to the drain.
4
Filling the water circuit.
5
Filling the domestic hot water tank.
6
Insulating the water piping.
7.8.2
Precautions when connecting the water
piping
INFORMATION
Also read the precautions and requirements in the
following chapters:
▪ General safety precautions
▪ Preparation
7.8.3
To connect the water piping
NOTICE
Do NOT use excessive force when connecting the piping.
Deformation of the piping can cause malfunctioning of the
unit.
To facilitate service and maintenance, 2 shut-off valves are provided.
Mount the valves on the space heating water inlet and space heating
water outlet. Mind their position: the integrated drain valves will only
drain the side of the circuit on which they are located. To be able to
only drain the unit, make sure the drain valves are positioned
between the shut‑off valves and the unit.
1
Install the shut-off valves on the space heating water pipes.
2
Screw the indoor unit nuts on the shut-off valve.
3
Connect the domestic hot water in and out pipes to the indoor
unit.
a
c
d
b
a
Space heating/cooling water out
b
Space heating/cooling water in
c
Domestic hot water out
d
Domestic cold water in (cold water supply)
NOTICE
It is recommended to install shut-off valves to domestic
cold water in and domestic hot water out connections.
These shut-off valves are field supplied.
Содержание Altherma EHVH/X04S18CB
Страница 103: ......
Страница 104: ...4P384973 1D 2018 07 Copyright 2015 Daikin...