11
|
Configuration
Installer reference guide
226
ERRA08~12E + EL23E
Daikin Altherma 3 R MT F
4P708478-1 – 2023.05
NOTICE
2 weeks to change.
After you activated BBR16, you only have 2 weeks to change its
settings (
BBR16 activation
and
BBR16 power limit
). After 2 weeks, the unit
freezes these settings.
Note:
This is different from the permanent power limitation, which is always
changeable.
BBR16 activation
#
Code
Description
[9.9.F]
[7-07]
BBR16 activation
:
▪
0:
disabled
▪
1:
enabled
BBR16 power limit
#
Code
Description
[9.9.G]
[N/A]
BBR16 power limit
: This setting can only
be modified via the menu structure.
▪
0 kW~25 kW, step 0.1 kW
Energy metering
Energy metering
If energy metering is performed by the use of external power meters, configure the
settings as described below. Select the pulse frequency output of each power
meter in accordance with the power meter specifications. It is possible to connect
up to 2 power meters with different pulse frequencies. If only 1 or no power meter
is used, select '
None
' to indicate the corresponding pulse input is NOT used.
#
Code
Description
[9.A.1]
[D‑08]
Electricity meter 1
:
▪
0
None
: NOT installed
▪
1
1/10kWh
: Installed
▪
2
1/kWh
: Installed
▪
3
10/kWh
: Installed
▪
4
100/kWh
: Installed
▪
5
1000/kWh
: Installed
[9.A.2]
[D‑09]
Electricity meter 2
:
▪
0
None
: NOT installed
▪
1
1/10kWh
: Installed
▪
2
1/kWh
: Installed
▪
3
10/kWh
: Installed
▪
4
100/kWh
: Installed
▪
5
1000/kWh
: Installed
In case of pulse meter for photovoltaic panels:
▪
6
100/kWh for PV panel
: Installed
▪
7
1000/kWh for PV panel
: Installed