background image

8 Hand-over to the user

Installation manual

38

EGSAH/X06+10UDA9W

Daikin Altherma 3 GEO

4P598591-1A – 2019.12

7.2.5

To perform an underfloor heating screed
dryout

Conditions: 

Make  sure  all  operation  is  disabled.  Go  to  [C]:

Operation

  and  turn  off 

Room

Space  heating/cooling

  and 

Tank

operation.

Conditions: 

▪ Make sure all operation is disabled. Go to [C] 

Operation

 and turn

off  [C.1] 

Room

,  [C.2] 

Space  heating/cooling

  and  [C.3] 

Tank

operation.

▪ Make  sure  [2.7]  and  [3.7] 

Emitter  type

  is  set  to 

Underfloor

heating

.

1

Set the user permission level to Installer. See 

"To

change the user permission level" 

[

4

 28].

2

Go to [A.4]: 

Commissioning

 > 

UFH screed dryout

.

3

Set a dryout program: go to 

Program

 and use the

UFH screed dryout programming screen.

4 Select 

OK

 to confirm.

Result: 

The underfloor heating screed dryout starts.

It stops automatically when done.

To stop the test run manually:

1

Go to 

Stop UFH screed dryout

.

2

Select 

OK

 to confirm.

NOTICE

To perform an underfloor heating screed dryout, room frost
protection needs to be disabled ([2‑06]=0). By default, it is
enabled  ([2‑06]=1).  However,  due  to  the  "installer-on-site"
mode (see "Commissioning"), room frost protection will be
automatically disabled for 36 hours after the first power-on.

If  the  screed  dryout  still  needs  to  be  performed  after  the
first  36  hours  of  power-on,  manually  disable  room  frost
protection  by  setting  [2‑06]  to  "0",  and  KEEP  it  disabled
until the screed dryout has finished. Ignoring this notice will
result in cracking of the screed.

NOTICE

For the underfloor heating screed dryout to be able to start,
make sure the following settings are met:

▪ [4‑00]=1

▪ [C‑02]=0

▪ [D‑01]=0

▪ [4‑08]=0

▪ [4‑01]≠1

Resume after power failure

If  power  is  restored  after  a  power  failure,  underfloor  heating  screed
dryout automatically resumes its operation.

7.2.6

To start or stop 10-day brine pump
operation

If  a  brine  buffer  vessel  is  part  of  the  brine  circuit,  or  in  case  a
horizontal brine loop is used, it may be required to let the brine pump
run continuously for 10 days after the system is commissioned. If 

10

day brine pump operation

 is:

▪ ON:  The  unit  operates  as  normal,  except  that  the  brine  pump

operates  continuously  for  10  days,  independent  of  compressor
status.

▪ OFF: Brine pump operation is linked to compressor status.

Conditions: 

  All  other  commissioning  tasks  have  been  completed

before starting the 

10 day brine pump operation

. After you have

done this, 

10 day brine pump operation

 can be activated in the

commissioning menu.

1

Set the user permission level to Installer. See 

"To

change the user permission level" 

[

4

 28].

2

Go to [A.6]: 

Commissioning

 > 

10 day brine pump

operation

.

3

Select 

On

 to start the 

10 day brine pump

operation

.

Result: 

 The 

10 day brine pump operation

starts.

During  the 

10  day  brine  pump  operation

,  the  setting  will  be

displayed  as  ON  in  the  menu.  Once  the  procedure  has  been
completed, it will change to OFF automatically.

NOTICE

The 10-day brine pump operation will only start if there are
no errors present on the main menu screen and the timer
will only count down if either an underfloor heating screed
dryout  is  started,  or  if  Space  heating/cooling  or  Tank
operation is enabled.

8

Hand-over to the user

Once the test run is finished and the unit operates properly, please
make sure the following is clear for the user:

▪ Fill in the installer setting table (in the operation manual) with the

actual settings.

▪ Make  sure  that  the  user  has  the  printed  documentation  and  ask

him/her to keep it for future reference. Inform the user that he can
find the complete documentation at the URL mentioned earlier in
this manual.

▪ Explain the user how to properly operate the system and what to

do in case of problems.

▪ Show the user what to do for the maintenance of the unit.

▪ Explain  the  user  about  energy  saving  tips  as  described  in  the

operation manual.

Содержание Altherma 3 GEO EGSAH10UDA9W

Страница 1: ...Installation manual Daikin Altherma 3 GEO English Installation manual Daikin Altherma 3 GEO EGSAH06UDA9W EGSAH10UDA9W EGSAX06UDA9W EGSAX10UDA9W...

Страница 2: ...o le prescrizioni per de acordo com o previsto em 10 11 12 13 14 15 16 17 18 under iagttagelse af bestemmelserne i enligt villkoren i gitt i henhold til bestemmelsene i noudattaen m r yksi za dodr en...

Страница 3: ...staava kyll stysl mp tila M C Kylm aine N Varmuuspainelaitteen asetus P bar Valmistusnumero ja valmistusvuosi katso mallin nimikilpi Maxim ln p pustn tlak PS K bar Minim ln maxim ln p pustn teplota TS...

Страница 4: ...3 5 13 To connect the brine low pressure switch 23 5 14 To connect the thermostat for passive cooling 24 5 15 LAN adapter 24 5 15 1 About the LAN adapter 24 5 15 2 Overview of electrical connections 2...

Страница 5: ...to facilitate the installation and configuration of heating systems To access Heating Solutions Navigator registration to the Stand By Me platform is required For more information see https professio...

Страница 6: ...The appliance shall be stored in a room without continuously operating ignition sources example open flames an operating gas appliance or an operating electric heater 3 1 1 Installation site requirem...

Страница 7: ...nel 5 Installer switch box cover 6 Main switch box cover Open 1 Remove the top panel 5 T25 2 Remove the user interface panel Open the hinges at the top and slide the user interface panel upwards NOTIC...

Страница 8: ...r for servicing The removal of the module will significantly reduce the weight of the unit This makes the unit easier to handle and carry 1 Open the following see 3 2 1 To open the indoor unit 47 1 Us...

Страница 9: ...step 2 in 3 2 2 To remove the hydro module from the unit 48 2 Close the shut off valves by turning the lever handles 4 3 Remove the lower hydro module cover See step 5 in 3 2 2 To remove the hydro mod...

Страница 10: ...e brine circuit Do NOT use Zn coated piping as this may lead to excessive corrosion See also 4 2 4 To fill the brine circuit 411 NOTICE In case of plastic pipes make sure they are fully oxygen diffusi...

Страница 11: ...off valve below the vessel 5 Remove the safety valve on top of the vessel 6 Top up the vessel with brine until it is approximately 2 3 filled 7 Reconnect the safety valve 8 Open the shut off valve be...

Страница 12: ...hot water 412 a b c d b a Space heating cooling water OUT 22 mm b Space heating cooling water IN 22 mm and shut off valve with integrated filter accessory c Domestic hot water hot water OUT 22 mm d D...

Страница 13: ...G3 section 3 56 Table 03 and worked example 9 After completing the installation the installer has to fill out the warning label on the tank with indelible ink The warning label can be found on the un...

Страница 14: ...icular small leaks Small leaks can easily be overseen but can cause damage to the unit and surroundings over a longer period of time NOTICE After water piping installation check all connections for le...

Страница 15: ...ermostat 3 for cooling heating operation 2 for heating only operation 0 75 mm Wires for wireless room thermostat 5 for cooling heating operation 4 for heating only operation 0 75 mm Maximum running cu...

Страница 16: ...without separate normal kWh rate power supply b C1 C5 C2 X5M C1 Preferential kWh rate power supply for the backup heater 1N or 3N C2 Preferential kWh rate power supply contact C5 Preferential kWh rate...

Страница 17: ...GRY BLU YLW GRN a Factory mounted power supply cable b Field wiring F1B Overcurrent fuse field supply Recommended fuse for 1N 4 pole 32 A fuse C curve Recommended fuse for 3N 4 pole 16 A fuse C curve...

Страница 18: ...surement is important Remote outdoor sensor cable 40 m delivered as accessory 9 B 2 Ext amb sensor offset overview field setting 2 0B 9 B 3 Averaging time overview field setting 1 0A 1 Connect the ext...

Страница 19: ...tricity meter with transistor output check the polarity The positive polarity MUST be connected to X5M 6 and X5M 4 the negative polarity to X5M 5 and X5M 3 1 Open the following see 3 2 1 To open the i...

Страница 20: ...anel 3 2 5 1 4 2 User interface panel 3 Front panel 4 Installer switch box cover 5 Main switch box cover 2 Connect the alarm output cable to the appropriate terminals as shown in the illustration belo...

Страница 21: ...tch box cover 2 Connect the alarm output cable to the appropriate terminals as shown in the illustration below Make sure to put wires 2 and 3 between the installer switch box and main switch box in a...

Страница 22: ...X2X1 L N X2 X1 a a Installation of EKRP1HBAA is required 3 Fix the cable with cable ties to the cable tie mountings 5 11 To connect the power consumption digital inputs Wires 2 per input signal 0 75 m...

Страница 23: ...onfiguration the indoor unit will ignore the safety thermostat contact INFORMATION The preferential kWh rate power supply contact is connected to the same terminals X5M 9 10 as the safety thermostat T...

Страница 24: ...LAN adapter 5 15 1 About the LAN adapter The indoor unit contains an integrated LAN adapter model BRP069A61 which allows for App control of the heat pump system Integration of the heat pump system in...

Страница 25: ...y management system a2 230 V AC detection voltage b To electricity meter c Factory mounted cable to indoor unit P1 P2 d To router via the factory mounted Ethernet cable outside of the unit Connections...

Страница 26: ...Measurement type Depends on the installation 1N AC meter 3N AC meter balanced loads 3N AC meter unbalanced loads INFORMATION It is required that the electricity meter has a pulse output that can meas...

Страница 27: ...f high energy tariffs Open Closed Forced ON Energy buffering in the domestic hot water tank and or the room WITHOUT power limitation Closed Closed For more information see the installer reference guid...

Страница 28: ...ferent methods However NOT all settings are accessible via both methods If so the corresponding table columns in this chapter are set to N A not applicable Method Column in tables Accessing settings v...

Страница 29: ...estic hot water or not and which tank is used This setting is read only Code Description 9 2 1 E 05 E 06 E 07 No DHW domestic hot water Integrated The backup heater will also be used for domestic hot...

Страница 30: ...towards a low temperature emitter Make sure you set the emitter types for the main zone 2 7 and for the additional zone 3 7 correctly in accordance with the connected emitter NOTICE An overpressure b...

Страница 31: ...tion 2 4 N A Setpoint mode Fixed WD heating fixed cooling Weather dependent When weather dependent operation is active low outdoor temperatures will result in warmer water and vice versa During weathe...

Страница 32: ...ensor on the North wall of the building If the outdoor temperature drops or rises the unit compensates instantly Thus the unit does not have to wait for feedback by the thermostat to increase or decre...

Страница 33: ...ing Domestic hot water X1 X2 Examples of outdoor ambient temperature Item Description Y1 Y2 Y3 Y4 Examples of desired tank temperature or leaving water temperature The icon corresponds to the heat emi...

Страница 34: ...2 A C 05 External room thermostat type for the main zone 1 1 contact The used external room thermostat can only send a thermo ON OFF condition There is no separation between heating or cooling demand...

Страница 35: ...Water pipe freeze prevention Benefit kWh power supply Power consumption control Energy metering Sensors Bivalent Alarm output Auto restart Power saving function Disable protections Overview field set...

Страница 36: ...Between the indoor unit and the valves if applicable Between the indoor unit and the room thermostat if applicable The system is properly earthed and the earth terminals are tightened The fuses or loc...

Страница 37: ...when ready 30 min To stop the test run manually 1 In the menu go to Stop test run 2 Select OK to confirm INFORMATION If the outdoor temperature is outside the range of operation the unit may NOT oper...

Страница 38: ...brine pump operation If a brine buffer vessel is part of the brine circuit or in case a horizontal brine loop is used it may be required to let the brine pump run continuously for 10 days after the s...

Страница 39: ...cal water conditions annual inspection of the integral line strainer pressure reducing valve cartridge and seating may be necessary c a b a Cartridge b Strainer c Calibration screw 1 Unscrew the plast...

Страница 40: ...e must be high enough Check if the water coming out of the relief valve is clean If it contains debris or dirt Open the valve until the discharged water does not contain debris or dirt anymore Flush a...

Страница 41: ...a pump to drain the tank via the access point 2 1 4 Tightening torques for installation Item Tightening torque Tube connection 30 N m Temperature and pressure relief valve 40 N m 9 4 To inspect the in...

Страница 42: ...m c1 Brine IN 28 mm c2 Brine OUT 28 mm d Shut off valve e Automatic air purge valve f Safety valve g Shut off valve h Manual air purge valve i Drain valve j Backup heater k Recirculation connection 3...

Страница 43: ...CB A3P On OFF thermostat A3P Heat pump convector A4P Digital I O PCB A4P Receiver PCB Wireless On OFF thermostat PC power circuit A6P Backup heater control PCB A7P Inverter PCB A8P Demand PCB A15P LAN...

Страница 44: ...ical meters Electricity meters For safety thermostat For safety thermostat Inrush Inrush current Max load Maximum load Normally closed Normally closed Normally open Normally open Safety thermostat con...

Страница 45: ...ial kWh rate unit power supply installation Only with EKGSPOWCAB Compressor power supply 230 V earth Only with EKGSPOWCAB POWER SUPPLY FIELD SUPPLY OPTIONAL PART Only for EKCSENS INDOOR UNIT STANDARD...

Страница 46: ...parts Contact your local Daikin dealer Installed by name address tel No completion date TECHNICAL SPECIFICATIONS EN12897 2016 Maximum water supply pressure to pressure reducing valve 16 bar Operating...

Страница 47: ......

Страница 48: ...4P598591 1A 2019 12 Copyright 2019 Daikin 4P598591 1 A 00000007 Verantwortung f r Energie und Umwelt...

Отзывы: