background image

7 Commissioning

Installation manual

37

EGSAH/X06+10UDA9W
Daikin Altherma 3 GEO
4P598591-1A – 2019.12

7.2.1

To perform an air purge on the water
circuit

Conditions: 

Make  sure  all  operation  is  disabled.  Go  to  [C]:

Operation

  and  turn  off 

Room

Space  heating/cooling

  and 

Tank

operation.

1

Set the user permission level to Installer. See 

"To

change the user permission level" 

[

4

 28].

2

Go to [A.3]: 

Commissioning

 > 

Air purge

.

3

Select 

OK

 to confirm.

Result: 

The air purge starts. It stops automatically

when air purge cycle is finished.

To stop the air purge manually:

1

Go to 

Stop air purge

.

2

Select 

OK

 to confirm.

7.2.2

To perform an air purge on the brine
circuit

There are two ways to perform an air purge on the brine circuit:

▪ with a brine filling station (field supply)

▪ with  a  brine  filling  station  (field  supply)  in  combination  with  the

unit’s own brine pump

In  both  cases,  follow  the  instructions  included  with  the  brine  filling
station. The second method should only be used when the air purge
on  the  brine  circuit  was  NOT  successful  using  only  a  brine  filling
station.  See  “To  perform  an  air  purge  with  a  brine  filling  station”  in
the installer reference guide for more information.

In  case  a  brine  buffer  vessel  is  present  in  the  brine  circuit,  or  if  the
brine  circuit  consists  of  a  horizontal  loop  instead  of  a  vertical
borehole, further air purging may be required. You can make use of
the 

10 day brine pump operation

See 

"7.2.6 To start or stop 10-

day brine pump operation" 

[

4

 38] for more information.

7.2.3

To perform an operation test run

Conditions: 

Make  sure  all  operation  is  disabled.  Go  to  [C]:

Operation

  and  turn  off 

Room

Space  heating/cooling

  and 

Tank

operation.

1

Set the user permission level to 

Installer

. See 

"To

change the user permission level" 

[

4

 28].

2

Go to [A.1]: 

Commissioning

 > 

Operation test

run

.

3

Select a test from the list. 

Example: 

Heating

.

4

Select 

OK

 to confirm.

Result: 

The test run starts. It stops automatically

when ready (±30 min).

To stop the test run manually:

1

In the menu, go to 

Stop test run

.

2

Select 

OK

 to confirm.

INFORMATION

If  the  outdoor  temperature  is  outside  the  range  of
operation,  the  unit  may  NOT  operate  or  may  NOT  deliver
the required capacity.

To monitor leaving water and tank temperatures

During test run, the correct operation of the unit can be checked by
monitoring its leaving water temperature (heating/cooling mode) and
tank temperature (domestic hot water mode).

To monitor the temperatures:

1

In the menu, go to 

Sensors

.

2

Select the temperature information.

7.2.4

To perform an actuator test run

Conditions: 

Make  sure  all  operation  is  disabled.  Go  to  [C]:

Operation

  and  turn  off 

Room

Space  heating/cooling

  and 

Tank

operation.

Purpose

Perform an actuator test run to confirm the operation of the different
actuators.  For  example,  when  you  select 

Pump

,  a  test  run  of  the

pump will start.

1

Set the user permission level to Installer. See 

"To

change the user permission level" 

[

4

 28].

2

Go to [A.2]: 

Commissioning

 > 

Actuator test run

.

3

Select a test from the list. 

Example: 

Pump

.

4

Select 

OK

 to confirm.

Result: 

The actuator test run starts. It stops

automatically when done (±30 min for 

Pump

,

±120 min for 

Brine pump

, ±10 min for other test

runs).

To stop the test run manually:

1

Go to 

Stop test run

.

2

Select 

OK

 to confirm.

Possible actuator test runs

Backup  heater  1

  test  (3  kW  capacity,  only  available  when  no

current sensors are used)

Backup  heater  2

  test  (6  kW  capacity,  only  available  when  no

current sensors are used)

Pump

 test

INFORMATION

Make  sure  that  all  air  is  purged  before  executing  the  test
run. Also avoid disturbances in the water circuit during the
test run.

Shut off valve

 test

Diverter  valve

  test  (3-way  valve  for  switching  between  space

heating and tank heating)

Bivalent signal

 test

Alarm output

 test

C/H signal

 test

DHW pump

 test

Backup  heater  phase  1

  test  (3  kW  capacity,  only  available

when current sensors are used)

Backup  heater  phase  2

  test  (3  kW  capacity,  only  available

when current sensors are used)

Backup  heater  phase  3

  test  (3  kW  capacity,  only  available

when current sensors are used)

Brine pump

 test

Содержание Altherma 3 GEO EGSAH10UDA9W

Страница 1: ...Installation manual Daikin Altherma 3 GEO English Installation manual Daikin Altherma 3 GEO EGSAH06UDA9W EGSAH10UDA9W EGSAX06UDA9W EGSAX10UDA9W...

Страница 2: ...o le prescrizioni per de acordo com o previsto em 10 11 12 13 14 15 16 17 18 under iagttagelse af bestemmelserne i enligt villkoren i gitt i henhold til bestemmelsene i noudattaen m r yksi za dodr en...

Страница 3: ...staava kyll stysl mp tila M C Kylm aine N Varmuuspainelaitteen asetus P bar Valmistusnumero ja valmistusvuosi katso mallin nimikilpi Maxim ln p pustn tlak PS K bar Minim ln maxim ln p pustn teplota TS...

Страница 4: ...3 5 13 To connect the brine low pressure switch 23 5 14 To connect the thermostat for passive cooling 24 5 15 LAN adapter 24 5 15 1 About the LAN adapter 24 5 15 2 Overview of electrical connections 2...

Страница 5: ...to facilitate the installation and configuration of heating systems To access Heating Solutions Navigator registration to the Stand By Me platform is required For more information see https professio...

Страница 6: ...The appliance shall be stored in a room without continuously operating ignition sources example open flames an operating gas appliance or an operating electric heater 3 1 1 Installation site requirem...

Страница 7: ...nel 5 Installer switch box cover 6 Main switch box cover Open 1 Remove the top panel 5 T25 2 Remove the user interface panel Open the hinges at the top and slide the user interface panel upwards NOTIC...

Страница 8: ...r for servicing The removal of the module will significantly reduce the weight of the unit This makes the unit easier to handle and carry 1 Open the following see 3 2 1 To open the indoor unit 47 1 Us...

Страница 9: ...step 2 in 3 2 2 To remove the hydro module from the unit 48 2 Close the shut off valves by turning the lever handles 4 3 Remove the lower hydro module cover See step 5 in 3 2 2 To remove the hydro mod...

Страница 10: ...e brine circuit Do NOT use Zn coated piping as this may lead to excessive corrosion See also 4 2 4 To fill the brine circuit 411 NOTICE In case of plastic pipes make sure they are fully oxygen diffusi...

Страница 11: ...off valve below the vessel 5 Remove the safety valve on top of the vessel 6 Top up the vessel with brine until it is approximately 2 3 filled 7 Reconnect the safety valve 8 Open the shut off valve be...

Страница 12: ...hot water 412 a b c d b a Space heating cooling water OUT 22 mm b Space heating cooling water IN 22 mm and shut off valve with integrated filter accessory c Domestic hot water hot water OUT 22 mm d D...

Страница 13: ...G3 section 3 56 Table 03 and worked example 9 After completing the installation the installer has to fill out the warning label on the tank with indelible ink The warning label can be found on the un...

Страница 14: ...icular small leaks Small leaks can easily be overseen but can cause damage to the unit and surroundings over a longer period of time NOTICE After water piping installation check all connections for le...

Страница 15: ...ermostat 3 for cooling heating operation 2 for heating only operation 0 75 mm Wires for wireless room thermostat 5 for cooling heating operation 4 for heating only operation 0 75 mm Maximum running cu...

Страница 16: ...without separate normal kWh rate power supply b C1 C5 C2 X5M C1 Preferential kWh rate power supply for the backup heater 1N or 3N C2 Preferential kWh rate power supply contact C5 Preferential kWh rate...

Страница 17: ...GRY BLU YLW GRN a Factory mounted power supply cable b Field wiring F1B Overcurrent fuse field supply Recommended fuse for 1N 4 pole 32 A fuse C curve Recommended fuse for 3N 4 pole 16 A fuse C curve...

Страница 18: ...surement is important Remote outdoor sensor cable 40 m delivered as accessory 9 B 2 Ext amb sensor offset overview field setting 2 0B 9 B 3 Averaging time overview field setting 1 0A 1 Connect the ext...

Страница 19: ...tricity meter with transistor output check the polarity The positive polarity MUST be connected to X5M 6 and X5M 4 the negative polarity to X5M 5 and X5M 3 1 Open the following see 3 2 1 To open the i...

Страница 20: ...anel 3 2 5 1 4 2 User interface panel 3 Front panel 4 Installer switch box cover 5 Main switch box cover 2 Connect the alarm output cable to the appropriate terminals as shown in the illustration belo...

Страница 21: ...tch box cover 2 Connect the alarm output cable to the appropriate terminals as shown in the illustration below Make sure to put wires 2 and 3 between the installer switch box and main switch box in a...

Страница 22: ...X2X1 L N X2 X1 a a Installation of EKRP1HBAA is required 3 Fix the cable with cable ties to the cable tie mountings 5 11 To connect the power consumption digital inputs Wires 2 per input signal 0 75 m...

Страница 23: ...onfiguration the indoor unit will ignore the safety thermostat contact INFORMATION The preferential kWh rate power supply contact is connected to the same terminals X5M 9 10 as the safety thermostat T...

Страница 24: ...LAN adapter 5 15 1 About the LAN adapter The indoor unit contains an integrated LAN adapter model BRP069A61 which allows for App control of the heat pump system Integration of the heat pump system in...

Страница 25: ...y management system a2 230 V AC detection voltage b To electricity meter c Factory mounted cable to indoor unit P1 P2 d To router via the factory mounted Ethernet cable outside of the unit Connections...

Страница 26: ...Measurement type Depends on the installation 1N AC meter 3N AC meter balanced loads 3N AC meter unbalanced loads INFORMATION It is required that the electricity meter has a pulse output that can meas...

Страница 27: ...f high energy tariffs Open Closed Forced ON Energy buffering in the domestic hot water tank and or the room WITHOUT power limitation Closed Closed For more information see the installer reference guid...

Страница 28: ...ferent methods However NOT all settings are accessible via both methods If so the corresponding table columns in this chapter are set to N A not applicable Method Column in tables Accessing settings v...

Страница 29: ...estic hot water or not and which tank is used This setting is read only Code Description 9 2 1 E 05 E 06 E 07 No DHW domestic hot water Integrated The backup heater will also be used for domestic hot...

Страница 30: ...towards a low temperature emitter Make sure you set the emitter types for the main zone 2 7 and for the additional zone 3 7 correctly in accordance with the connected emitter NOTICE An overpressure b...

Страница 31: ...tion 2 4 N A Setpoint mode Fixed WD heating fixed cooling Weather dependent When weather dependent operation is active low outdoor temperatures will result in warmer water and vice versa During weathe...

Страница 32: ...ensor on the North wall of the building If the outdoor temperature drops or rises the unit compensates instantly Thus the unit does not have to wait for feedback by the thermostat to increase or decre...

Страница 33: ...ing Domestic hot water X1 X2 Examples of outdoor ambient temperature Item Description Y1 Y2 Y3 Y4 Examples of desired tank temperature or leaving water temperature The icon corresponds to the heat emi...

Страница 34: ...2 A C 05 External room thermostat type for the main zone 1 1 contact The used external room thermostat can only send a thermo ON OFF condition There is no separation between heating or cooling demand...

Страница 35: ...Water pipe freeze prevention Benefit kWh power supply Power consumption control Energy metering Sensors Bivalent Alarm output Auto restart Power saving function Disable protections Overview field set...

Страница 36: ...Between the indoor unit and the valves if applicable Between the indoor unit and the room thermostat if applicable The system is properly earthed and the earth terminals are tightened The fuses or loc...

Страница 37: ...when ready 30 min To stop the test run manually 1 In the menu go to Stop test run 2 Select OK to confirm INFORMATION If the outdoor temperature is outside the range of operation the unit may NOT oper...

Страница 38: ...brine pump operation If a brine buffer vessel is part of the brine circuit or in case a horizontal brine loop is used it may be required to let the brine pump run continuously for 10 days after the s...

Страница 39: ...cal water conditions annual inspection of the integral line strainer pressure reducing valve cartridge and seating may be necessary c a b a Cartridge b Strainer c Calibration screw 1 Unscrew the plast...

Страница 40: ...e must be high enough Check if the water coming out of the relief valve is clean If it contains debris or dirt Open the valve until the discharged water does not contain debris or dirt anymore Flush a...

Страница 41: ...a pump to drain the tank via the access point 2 1 4 Tightening torques for installation Item Tightening torque Tube connection 30 N m Temperature and pressure relief valve 40 N m 9 4 To inspect the in...

Страница 42: ...m c1 Brine IN 28 mm c2 Brine OUT 28 mm d Shut off valve e Automatic air purge valve f Safety valve g Shut off valve h Manual air purge valve i Drain valve j Backup heater k Recirculation connection 3...

Страница 43: ...CB A3P On OFF thermostat A3P Heat pump convector A4P Digital I O PCB A4P Receiver PCB Wireless On OFF thermostat PC power circuit A6P Backup heater control PCB A7P Inverter PCB A8P Demand PCB A15P LAN...

Страница 44: ...ical meters Electricity meters For safety thermostat For safety thermostat Inrush Inrush current Max load Maximum load Normally closed Normally closed Normally open Normally open Safety thermostat con...

Страница 45: ...ial kWh rate unit power supply installation Only with EKGSPOWCAB Compressor power supply 230 V earth Only with EKGSPOWCAB POWER SUPPLY FIELD SUPPLY OPTIONAL PART Only for EKCSENS INDOOR UNIT STANDARD...

Страница 46: ...parts Contact your local Daikin dealer Installed by name address tel No completion date TECHNICAL SPECIFICATIONS EN12897 2016 Maximum water supply pressure to pressure reducing valve 16 bar Operating...

Страница 47: ......

Страница 48: ...4P598591 1A 2019 12 Copyright 2019 Daikin 4P598591 1 A 00000007 Verantwortung f r Energie und Umwelt...

Отзывы: