Final Adjustment

12

. If the chamber height has been miscalculated and the levels can not be altered by adjusting the bedding of the frame, it is possible to cut 

the top section of the chamber horizontally to correct the level.

12.1

. Simply mark the chamber section that requires adjustment and cut by either using a handsaw or a disc cutter.

 

12.2

. The required section can then be bedded onto the next section using the standard processes.

 

12.3

. The voids in the top section should now be filled with lean mix concrete to give a solid base for the frame to be bedded on.

Frame and Cover

13

. Once the chamber is backfilled the frame and cover can be fitted.

13.1

. Place the frame on top of the chamber to check that there is adequate space for a mortar 

bed. The depth of acceptable bed can vary between client so referral to the appropriate 

requirements should be taken. Generally mortar beds can range from 10 to 40mm in 

thickness. Pack the frame to the required height using suitable approved materials and 

check that the frame is in a coplanar state.

13.2

. Remove the frame and apply the mortar bed. This should be approximately 10mm 

higher 

than required and 25mm greater than the spread of the underside of the frame.

13.3

. Carefully position the frame on to the mortar bed, taking care that the inside faces of 

the frame line up with the edges of the chamber. If using a rising frame this should 

happen automatically.

 

13.4

. Gently tap the frame into the mortar bed until the correct level is achieved, always 

checking that the frame is in a coplanar state.

 

13.5

. Remove any excess mortar that has squeezed into the chamber and trowel mortar over 

the exterior flanges/grout bars at a 45° angle away from the frame.

 

13.6

. After the mortar has sufficiently cured the covers can be installed. (The use of epoxy 

resin 

mortars can be used and these can have a dramatic effect at reducing curing times. 

Please check with client about approval before use).

Reinstatement

14

. The finished surface can now be reinstated around the chamber.

Other Notes

 

15

. STAKKAbox™ access chambers can be supplied as a fixed-depth unit which will require suitable lifting requirements if planned to be

 lifted as a single unit. Lifting eyes, frames or other arrangements can be installed in-factory to accommodate mechanical lifting.

Содержание stakkabox

Страница 1: ...INSTALLATION GUIDE STAKKAbox Range General guide www cubis systems com 44 0 28 38 313 100 techsupport cubisindustries com ...

Страница 2: ...h laws regulations codes or orders of such authorities the customer shall be responsible for the violations thereof and shall bear the costs expense and damages attributable to its failure to comply with the provisions of such laws ordinances rules regulations codes or orders Reproduction of the material herein is not permitted without the written consent of CUBIS Industries NOTES ON APPLICATION T...

Страница 3: ... the correct loading as dictated by European standards or any other relevant authority CUBIS Industries manufacture a range of covers and frames engineered to work in conjunction with its chambers Covers and frames that are not supplied by CUBIS should be agreed to be fit for purpose prior to installation as this might adversely affect the quality of the installation HEALTH AND SAFETY In areas whe...

Страница 4: ...m ring section is now carefully positioned on the base If the chamber system does not have a preformed base then the ring should be gently tapped so that it beds down into the base by approximately 10mm The correct orientation of the chamber ring is with the horizontal lip to the bottom Check that the ring is level and at the correct depth If a concrete base is being used the concrete can be float...

Страница 5: ...xisting duct 8 3 In both cases it is important that a complete ring is installed either side of the cut ring section Wall Furniture Security Systems 9 Wall furniture can be installed at this stage if not already factory fitted 9 1 Mark the position of the furniture as required by the clients specification on the chamber walls drill 11mm holes and fix the furniture with the bolts supplied 9 2 If us...

Страница 6: ...ound of the chamber can now take place Backfilling is formed in layers and should be completed to the top of the chamber or in the case of a roadway construction to the underside of the blacktop construction Refer to Table 1 for the recommended backfill material and required width of material Refer to Specification for the Reinstatement of Openings in Highways Appendix A8 for the depth of layers a...

Страница 7: ...ate 13 2 Remove the frame and apply the mortar bed This should be approximately 10mm higher than required and 25mm greater than the spread of the underside of the frame 13 3 Carefully position the frame on to the mortar bed taking care that the inside faces of the frame line up with the edges of the chamber If using a rising frame this should happen automatically 13 4 Gently tap the frame into the...

Страница 8: ...compacted thickness up to for compacted thickness up to 100mm1 50mm 200mm1 00mm1 50mm 200mm Vibrotamper 50 kg minimum 48 N P4 8N P Single Drum 1000 2000 kg m 8 NP NP 6N PN P 2000 3500 kg m 36N P3 57 Over 3500 kg m 346 346 Twin Drum 600 1000 kg m NP NP NP 6N PN P 1000 2000 kg m 48N P 36N P Over 2000 kg m 235 234 1400 1800 kg m2 N PN PN P5 NP NP Over 1800 kg m2 36N P3 57 Notes 1 2 3 4 Vibrotamper 25...

Страница 9: ...0mm of compacted stone MOT1 Bracing required on chambers with side wall lengths greater than 600mm Compacted MOT1 stone or lean mix concrete 3 C250 1200 150mm or width of compacting equipment 150mm of lean mix concrete C40 Bracing required on chambers with side wall lengths greater than 600mm Minimum 150mm C40 concrete 4 D400 2000 200mm or width of compacting equipment 150mm of lean mix concrete C...

Страница 10: ...10 DIAGRAM 1 ...

Страница 11: ...11 DIAGRAM 2 Typical detail of a hard shoulder showing the location of some installation groups ...

Страница 12: ...ntact us Head Office 4 Silverwood Industrial Estate Lurgan Co Armagh BT66 6LN Northern Ireland Telephone 44 0 28 38 313 100 Email techsupport cubisindustries com Web www cubis systems com v 1 3 01 02 2016 ...

Отзывы: