4 COMMISSIONING
4.1
PRE-COMMISSIONING TASKS
After equipment installation, perform the following steps before equipment powering and commissioning:
Check the expected voltage, current and power levels do not violate any ratings.
Visually inspect the power connection within the equipment. Ensure that the power cable is correctly
and securely connected, including grounding wire, RF cable and other cables.
Check grounding connection and verify that the ground resistance is less than 5
Ω.
Test the antenna system and ensure the echo loss within working frequency is less than -14dB
(VSWR<1.5).
4.2
RFU LED INDICATOR
Three diagnostic LEDs are located on MCU panel; each indicates the status of a particular function:
Figure 23:
RFU LEDs on Outer Window
Table 7: RFU LEDs
Identifier
Colour
Indication
PWR
Green
Power indicator. ON = power on; OFF = power off.
RUN
Green
Operation indicator, flashes every second to indicate normal operation.
ALM
Red
Alarm indicator. ON = alarm; OFF = no alarm.