9.1.2.2. Fault
test
In order to test that the fault function is working properly, the following operations must be
carried out:
Note: Any connection or movement of the control panel must be carried out with the
panel disconnected, both from the power supply, and from the batteries.
1) Check that Common-Normally Open (NO) Fault contacts are electrically open.
2) An open line or crossed line fault occurs in one of the zones, verifying that:
a. The general fault indication led “D”, and fault “Q” of this zone is activated
whenever a maximum time of 10 seconds has passed (see chapter 2.1.1).
Note: The indicator led “Q” activates fix or flashes according to the open or
crossed line fault respectively.
b. Common-Normally Open (NO) Fault contacts are shorted and the fault relay
indicator led “G” illuminates once the configured delay time is passed.
3) Resetting control panel. All the indicator leds must be disabled with the exception of “B”
power supply (see chapter 2.1.1).
4) Check that Common-Normally Open (NO) Fault contacts are electrically open.
5) Repeat operations 2 to 4 with all active zones.
6) Cause an open line or crossed line fault at the sounder output, verifying that:
a. The general fault indication leds “D” is activated, and sounder relay "F" flashes
whenever a maximum time of 10 seconds has passed (see chapter 2.1.1).
b. Common-Normally Open (NO) Fault contacts are shorted and the fault relay
indicator led “G” illuminates once the configured delay time is passed.
7) Repeat operation 6 with the other sounder output.
8) Reset of control panel. All the indicator leds must be disabled with the exception of “B”
power supply (see chapter 2.1.1).
9) Check that Common-Normally Open (NO) Fault contacts are electrically open.
10) Carry out the “Battery Test" operations of section 9.1.2.3 to check the fault function on
them.