CS 3-Phase Installation Manual
Page 22
Cable Changes or Replacement:
• When connecting the output cable, verify that both of
the 120V AC (
LINE 1
and
LINE 2)
conductors and the
LINE 3
conductor all pass through the CCID sense
coil, as shown
Figure 9.
• The
GROUND
conductor should go to the Vehicle
Ground terminal lug located near the rear wall of the
chassis, and should NOT pass through the CCID coil.
• Connect the
PILOT
line to the small gauge blue
Anderson connector. The pilot line must not pass
through the
CCID
sense coil.
When the conductors are connected, the circuit breaker can be
turned on to power the unit. When power is first applied, the unit
will go through an initial self-testing sequence when it will check
the CCID, Ground Monitor, and other internal circuitry. The
Diagnostic LED in the lower left corner of the board will then
blink. The unit is ready for use. Plugging the vehicle charging
connector into a vehicle should initiate a sequence that will close
the contactor, and charging will begin. The unit may be tested
without plugging it into a vehicle. Simply press and hold the
CHARGE TEST buttons simultaneously and measure the charging
connector output with a DVM.
Figure 9. Vehicle Cable Wiring Diagram for 3-Phase AC Charging
NOTE: Torque specs vary
by configuration and are
specified on the inside of
the CS 3-Phase door.