4.3 Install Front Leg and Back Leg
4.3.1 Fix the Front Leg or
Back Leg on MT-Rail along
length direction and fasten
with Bolts M8*20 as shown in
Figure 6 and 7.
Note: please pay attention to
the installation direction of
Front Leg and Back Leg.
Recommended torque for
M8*20 is 18-20 N·m.
Figure 6 Figure 7
4.4 Install PV module
4.4.1 Place the PV module
on Front Leg and Back Leg
and fasten with End Clamp
and Inter Clamp tightly as
shown in Figure 8 and 9.
Recommended torque for
Bolts M8 of End and Inter
Clamp is 18-20 N·m.
Figure 8 Figure 9
4.5 Install Wind Deflector
4.5.1 Fix the Wind Deflector
Connector on Back Leg of
the last row and fasten with
Bolts M8*20 tightly as shown
in Figure 10.
Recommended torque for
Bolt M8*20 is 18-20 N·m.