4.2.3 Use U-bolt M8*58 to lock Wind
Deflector tightly as shown in Figures
7 and 8.
Recommended torque
:
8-9 N·m for U-bolt M8*58
4.2.4 After Wind Deflector and
Ballast bar are installed, load ballast
orderly. Ballast height should be no
more than 145mm as shown in
Figure 9.
(
If Wind Deflector is not required,
please ignore Step 4.2.1 to 4. 2.3
)
Figure 7 Figure 8
Figure 9
4.3
.
Install PV modules and Module Clamp 40
4.3.1 Rotate the right part of Support
Leg to the required position as
shown in Figure 10.
Figure 10
1. Nut
2. Washer
3. Plain washer
4. Fixing plate