Installation Guide / Grounding System

7

Code-Compliant Planning and Installation Guide V 1.1 - Complying with AS/NZS1170.2-2011 AMDT 2-2016

It is required to install one Grounding Lug per row of rail. The recommended fasten torque of the bolt M8*25 is  
16~20 N·m.

Grounding Lug Installation

- Installation Instructions -

Figure 17

Figure 18

Figure 19

Once grounding lug fixing with rail, insert U-Shape Copper Channel into 
grounding lug as shown in Figure 17. Strip earthing cable (the maximum size is 
10 mm2), insert the conductor into the Copper Channel and tighten the bolt 
M6*14 with 5~6 N·m to ensure the earthing cable is tight.

Note: Please check the electrical resistance between rail and earthing cable 
conductor to ensure the bonding is made.

There are three options for Grounding Lug installation.

Option 1

Fix the Grounding Lug into the top channel of Rail as shown in Figure 18.

Option 2

Fix the Grounding Lug into the top channel of Rail where just under the PV 
Module as shown in Figure 19. Total height of grounding lug allows installation 
under 30 mm high PV module. 

Option 3

Fix the Grounding Lug at the side channel of Rail as shown in Figure 20.

Figure 20

Содержание PV-ezRack Grounding system

Страница 1: ...Grounding System Code Compliant Planning and Installation Guide V 1 1 Complying with AS NZS1170 2 2011 AMDT 2 2016 Last Updated Apr 2022...

Страница 2: ...ck Product Warranty on our website Introduction Complying with all applicable local or national building codes including any that may supersede this manual Ensuring that PV ezRack and other products a...

Страница 3: ...Hex Head drive bit Torque Spanner Tape String Marker Pen Spanner Tools and Components Components ER EC ST Standard End Clamp ER IC ST Standard Inter Clamp C U 30 46 G Universal Clamp with Grounding cl...

Страница 4: ...the grounding clips at the positions marked X in Figure 1 where the number of Grounding Clips number of PV Modules Figure shows 4 x PV Modules requiring 4 x grounding clips When there is an odd number...

Страница 5: ...clips are the same as those for 2 rows of rails There are two types of clamps for PV Modules Installation Option 1 Standard Inter and End Clamps Place the first PV Module on the Rail according to you...

Страница 6: ...mes of PV Modules are completely pressed against End and Inter Clamps and Grounding Clips Visually check that Grounding Clips are positioned properly Grounding Clips are intended for SINGLE USE ONLY O...

Страница 7: ...l Clamp into the rail channel and slightly lift the framed PV Module to ensure the Grounding Clip is properly positioned as shown in Figure 14 Note The gap between two adjacent PV Modules generated by...

Страница 8: ...mum size is 10 mm2 insert the conductor into the Copper Channel and tighten the bolt M6 14 with 5 6 N m to ensure the earthing cable is tight Note Please check the electrical resistance between rail a...

Страница 9: ...St Clayton VIC 2168 Australia Phone 61 3 9239 8088 Email sales clenergy com au Web www clenergy com au Clenergy Clenergy_global ClenergyClub Clenergy ClenergyGlobal ClenergyClub ClenergyAUS A Clenergy...

Отзывы: