Installation Guide / Grounding System
6
Code-Compliant Planning and Installation Guide V 1.1 - Complying with AS/NZS1170.2-2011 AMDT 2-2016
Place the first PV Module on the Rails and apply the Universal Clamp as the End Clamp and fasten slightly. Make sure
the frame of the PV Module is fully in contact with the Universal Clamp as shown in Figures 12 and 13. Visually check
the Universal Clamp and PV module are properly installed.
When using as an Inter Clamp, click the Universal Clamp into the rail
channel and slightly lift the framed PV Module to ensure the Grounding
Clip is properly positioned as shown in Figure 14.
Note: The gap between two adjacent PV Modules generated by universal clamp is 20mm. The recommend torque
for Universal Clamp as End Clamp is 13~14 N·m. The recommend torque for Universal Clamps as Inter Clamp is 16~20
- Installation Instructions -
Figure 12
Figure 13
Figure 14
Loosely place the next framed PV Module into the other side of the Universal Clamp. Ensure the Grounding Clip is
properly positioned, and the frame of the PV Module is in proper contact with Universal Clamp as shown in Figures 15
and 16.
Figure 15
Figure 16
20mm