Installation Guide /  Grounding System

6

Code-Compliant Planning and Installation Guide V 1.1 - Complying with AS/NZS1170.2-2011 AMDT 2-2016

Place the first PV Module on the Rails and apply the Universal Clamp as the End Clamp and fasten slightly. Make sure 
the frame of the PV Module is fully in contact with the Universal Clamp as shown in Figures 12 and 13. Visually check 
the Universal Clamp and PV module are properly installed.

When using as an Inter Clamp, click the Universal Clamp into the rail 
channel and slightly lift the framed PV Module to ensure the Grounding 
Clip is properly positioned as shown in Figure 14.

Note: The gap between two adjacent PV Modules generated by universal clamp is 20mm. The recommend torque 
for Universal Clamp as End Clamp is 13~14 N·m. The recommend torque for Universal Clamps as Inter Clamp is 16~20 

- Installation Instructions -

Figure 12

Figure 13

Figure 14

Loosely place the next framed PV Module into the other side of the Universal Clamp. Ensure the Grounding Clip is 
properly positioned, and the frame of the PV Module is in proper contact with Universal Clamp as shown in Figures 15 
and 16.

Figure 15

Figure 16

20mm

Содержание PV-ezRack Grounding system

Страница 1: ...Grounding System Code Compliant Planning and Installation Guide V 1 1 Complying with AS NZS1170 2 2011 AMDT 2 2016 Last Updated Apr 2022...

Страница 2: ...ck Product Warranty on our website Introduction Complying with all applicable local or national building codes including any that may supersede this manual Ensuring that PV ezRack and other products a...

Страница 3: ...Hex Head drive bit Torque Spanner Tape String Marker Pen Spanner Tools and Components Components ER EC ST Standard End Clamp ER IC ST Standard Inter Clamp C U 30 46 G Universal Clamp with Grounding cl...

Страница 4: ...the grounding clips at the positions marked X in Figure 1 where the number of Grounding Clips number of PV Modules Figure shows 4 x PV Modules requiring 4 x grounding clips When there is an odd number...

Страница 5: ...clips are the same as those for 2 rows of rails There are two types of clamps for PV Modules Installation Option 1 Standard Inter and End Clamps Place the first PV Module on the Rail according to you...

Страница 6: ...mes of PV Modules are completely pressed against End and Inter Clamps and Grounding Clips Visually check that Grounding Clips are positioned properly Grounding Clips are intended for SINGLE USE ONLY O...

Страница 7: ...l Clamp into the rail channel and slightly lift the framed PV Module to ensure the Grounding Clip is properly positioned as shown in Figure 14 Note The gap between two adjacent PV Modules generated by...

Страница 8: ...mum size is 10 mm2 insert the conductor into the Copper Channel and tighten the bolt M6 14 with 5 6 N m to ensure the earthing cable is tight Note Please check the electrical resistance between rail a...

Страница 9: ...St Clayton VIC 2168 Australia Phone 61 3 9239 8088 Email sales clenergy com au Web www clenergy com au Clenergy Clenergy_global ClenergyClub Clenergy ClenergyGlobal ClenergyClub ClenergyAUS A Clenergy...

Отзывы: