4.1.5 Make sure the PV
module is placed properly
and levelly, and then slide
the end clamps into the
front
and
rear
legs
respectively to fix the PV
module. Fasten the end
clamps as shown in Fig. 6.
Recommended
tightening
torque
for
M8
bolt:
16-20N·m
4.1.6 Slide the inter clamp
into the front and rear legs
of the first PV module, as
shown in Fig. 7.
If grounding installation is
required, the grounding clip
shall be fixed in the inter
clamp, as shown in Fig. 8.
4.1.7 Place the second PV
module on the front and
rear legs, with the frame
pressed against the limiting
edges of the inter clamp
and the front leg, and then
fasten the inter clamp as
shown in Fig. 9 & 10.
Recommended
tightening
torque
for
M8
bolt:
16-20N·m
Fig. 6
Fig. 7
Fig. 8
Fig. 9