SENTINEL MEDIA METERING VALVE
Page 3
2.7
Attach the quick coupling and nipple to the wye.
2.8
Control Hose Connections
2.8.1
If a Clemco remote control with ACS control
handle is used, connect the “single” control line to the
fitting on the upper body as shown in Figure 1. Refer to
the blast machine and remote control manuals for set-up
and operation of the particular equipment.
2.8.2
If other machines or control systems are used,
the valve should have been ordered with the ACS. Note:
the ACS valve and fittings are shown under accessories
in Section 9.2. Refer to Figures 2 while making the
following changes:
Figure
2
2.8.2.1
Remove the fitting on the upper body cylinder
port.
2.8.2.2
Screw the 1/8" hex nipple provided, into the
"CYL" port of the ACS toggle valve, and attach it to the
upper body.
2.8.2.3
Install the fitting removed in the previous step,
(or one that is compatible with the system used), into the
"IN" port of the ACS valve.
2.8.2.4
If the Sentinel is installed on a manually-
operated blast machine, such as in an automated
system, connect an air line between the "IN" port fitting
and a tee installed before the machines air-inlet valve.
Refer to the top illustration in Figure 2.
2.8.2.5
If the Sentinel is connected to a remote system,
connect the air line from the "IN" port fitting to a
controlled air line (one that is on the controlled side of
the remote control air line, which will pressurize when
the control handle is pressed). One method is to tee off
the inlet or outlet valves of the remote system. Doing so
will close the valve when the remote controls
depressurize the blast machine, resulting in a smoother
start when the machine is re-pressurized. Refer to the
bottom illustration in Figure 2.
Install a tee for the
ACS valve before the
inlet valve.
Air flow
Air supply hose to
the cut-off valve is
supplied by the
Flange Adaptor without
Inspection opening
ACS cut-off valve.
Connection with manually-operated machine
Flange Adaptor with
Inspection opening
Air supply hose to the
cut-off valve is supplied
by the user.
This line must be tied
into the remote controls,
controlled-air circuit.
Connection with remote-controlled machine
Figure
3