Pull the length of cable you intend to open through the sealcon and out
of the cabinet. Clearfield recommends 15 feet of opened cable to work
with inside the cabinet (12 feet of slack and 3 feet for splicing in the
cassette). Open the cable.
8.
Optionally, group the buffer tubes to be spliced and fully insert
them into one of the mesh sleeves (snake skin) enclosed in the
ship along hardware. This will help to control the bundle while
routing and storing.
10.
Tighten the dome nut on the sealcon securely, being careful not to
damage the threads.
9.
Mark the buffer tubes 12 feet from the outer jacket and staggering the marks 1” shorter for each buffer tube (12’ blue, 11’
11” orange, 11’ 10” green, etc.). This will allow for the different lengths required for each buffer tube to reach its cassette
after storing the slack around the spools in the cabinet.
11.