12
Select a location:
There are several considerations when selecting a location for the boiler:
(1) Do not obstruct shop personnel or equipment
(2) Find a location where the boiler can easily be moved into place.
(3) The installation must meet the clearance to combustible material requirements (Figure 9)
(4) The location must be safely accessible for maintenance and service
(5) The installation must comply with all local codes and regulations
(6) Keep the stack / chimney system simple. A complicated stack with multiple elbows and
long horizontal runs will reduce the natural draft of the unit which can damage critical
burner components.
Figure 9: Clearances to Combustible Materials
Minimum Distances from Combustible Materials
WARNING:
Carefully follow all installation instructions for safe and efficient operation.
BOILER INSTALLATION
Front (Burner)
18” (48” for service clearance)
Back
18” (36” for service clearance)
Side
6”
Top
18”
Chimney Connection
18”
CE-340 BOILER
CLEARANCE)
(FOR SERVICE
FRONT 48"
BOTTOM 6"
CE70078
SIDE 6"
CLEARANCE)
(FOR SERVICE
BACK 36"
STACK 18"
TOP 18"
Содержание CE-340
Страница 2: ...7 3 13 Part 70006 Underwriters Laboratories File MH48829 ...
Страница 35: ...BOILER DIMENSIONS 35 57 5 42 5 67 with Burner 34 0 CE70077 50 ...
Страница 40: ...40 1 4 12 6 15 9 10 14 3 2 11 5 13 8 7 Nozzle Adapter Heater Block Assembly ...
Страница 42: ...42 2 5 7 6 4 5 3 12 11 9 8 10 1 CE70058 CE 4 Manifold Block Assembly ...
Страница 44: ...44 26 14 9 23 2 8 7 6 12 20 13 21 19 18 17 16 15 1 5 3 4 10 22 25 11 24 CE70050 Metering Pump Assembly ...
Страница 46: ...46 CE 340 Boiler 25 27 26 28 24 21 22 23 20 14 13 12 11 10 9 8 7 6 5 4 1 2 3 15 16 17 18 CE70101 19 ALT ALT ...