4-3
Cisco Network Convergence System 6000 Series Routers Unpacking, Moving, and Securing Guide
OL-29233-01
Chapter 4
Unpacking Chassis Components
Step 4
Carefully move the chassis into place over the bolt holes. See the
“Moving the Unpacked Chassis”
section on page 3-5
for details on moving the chassis with the dolly.
Note
Where side clearance is not enough to use the dolly, you must first lower the chassis to the floor
and then slide it into place.
Step 5
Lock the dolly caster anti-rotation and brake systems.
Step 6
With a person on each side of the chassis, turn all four lifting cranks of the dolly counterclockwise slowly
to lower the chassis to the floor.
Note
The dolly has four separate lifting cranks, each of which works independently when lifting or
lowering the chassis. It is best to turn the lifting cranks simultaneously when lifting the chassis
so as to not put undue stress on the chassis frame or dolly and reduce the risk of tipping too far.
Step 7
Remove the dolly from the chassis.
Warning
Do not permanently locate the equipment on the dolly. Safely store the dolly after use.
Statement 357
Step 8
Insert all anchor bolts.
Step 9
Tighten all bolts and nuts.
Unpacking Chassis Components
The remaining shipping boxes and pallets are now ready to be delivered from the receiving/shipping
dock or a site holding area to the final location of the chassis.
Steps
Step 1
If possible, move the pallets to the same location as the unpacked and secured chassis. If not possible,
move the individual boxes containing the various components to the chassis location.
Note
All components are packaged separately. Cards are attached and installed on a wooden board
insert held in place by captive Phillips screws.
Step 2
Unpack all primary pallet parts from the packaging, and set the parts aside for installation.
Step 3
Unpack all secondary pallet parts from the packaging, and set the parts aside for installation.
Note
Do not unpack individual cards until you are ready to install the cards in the chassis.