Date
Time
Verified By
Planning Activity
Task No.
Environmental evaluation:
• Ambient temperature
• Humidity
• Altitude
• Atmospheric
contamination
• Air flow
2
Power Evaluation:
• Input power type
• Power receptacles
1
• Receptacle proximity to
the equipment
• Dedicated circuit for
power supply
• Dedicated (separate)
circuits for redundant
power supplies
• UPS
2
for power failures
3
Grounding evaluation:
• Circuit breaker size
• CO ground (AC-
powered systems)
4
Cable and interface
equipment evaluation:
• Cable type
• Connector type
• Cable distance
limitations
• Interface equipment
(transceivers)
5
Cisco MDS 9396T Multilayer Fabric Switch Hardware Installation Guide
60
Site Planning and Maintenance Records
Site Planning and Maintenance Records