Section 360-080-102

5

Step

System Response

Action

13.

Once the trunk processing LED has extinguished,

select Status 

 Retrieve T1 Parameters.

The LP LED should turn on and the following infor-

mation should be displayed:

Status of the Incoming Primary T1

Line

Card Type:

T1

Operation Mode: Normal Mode
Timing Source: Internal Timing
Frame Format:

ESF

Line Code:

B8ZS

Automatic Detect Mode: No
LBO: 0

110

CGA Process Mode: Normal

Remote Control Method: Using Facility
Data Link

Status:Loopback (Out of Service)

14.

Release the T1 loopback.

Verification of the control system is complete.

5.

VERIFYING SYSTEM ALARMS

Use the following steps to verify system alarms.

Step

Action

System Response

1.

Perform a primary T1 near-end line loopback.

Verify that the TP LED is extinguished and no

visual or audible alarms exist.

2.

Release the T1 loopback.

Verify that there are visual and audible alarms.

3.

View the alarm status on the craft terminal and/or

NMS.

Display should show the correct alarm status.

4.

Press the ACO switch on the T1-S.

Verify that the audible alarm stops.

6.

VOICE CARD ACCEPTANCE TESTS

Use the following procedures to verify voice cards AFTER all the previous acceptance testing (electrical connec-

tions, system turn-up, control verification and system alarms) has been performed. Refer to the 

T1 Controller with

SNMP

 document for T1 pinouts.

Note:

All the following procedures are used for both audio and signaling.

6.1

FXS Card Acceptance Test

Step

Action

System Response

1.

Make sure that the ICB is turned up and operating.

2.

Install the FXS card per its documentation.

All LEDs on the card should light, flash, and then

turn off.

3.

Log in to the NMS or craft interface and verify that

the FXS card is recognized in the proper chassis

slot and the first-time boot-up configuration is FXS/

LS.

Содержание 360-80

Страница 1: ...echnical specifications herein subject to change without notice Page 1 of 9 360 80 Intelligent Channel Bank Turn Up and Acceptance Test Procedure CONTENTS PAGE Part 1 GENERAL 2 Part 2 VERIFYING ELECTR...

Страница 2: ...the Shelf documentation for the proper procedure Figure 1 displays the shelf rear panel 2 Apply power to the shelf 3 Locate the power terminal block on the rear see Figure 1 of the ICB Using a voltmet...

Страница 3: ...ID PWR Figure 2 T1 Controller Unit Front Panel 4 CONTROL VERIFICATION To get the information displayed as shown the control verification tests should be done with alarms active Control verification is...

Страница 4: ...th the NMS software installed con nect the ethernet from the PC to the network con trol terminal J2 on the rear of the T1 S 3 Activate the NMS software on the PC The NMS may start with the window mini...

Страница 5: ...rms exist 2 Release the T1 loopback Verify that there are visual and audible alarms 3 View the alarm status on the craft terminal and or NMS Display should show the correct alarm status 4 Press the AC...

Страница 6: ...nd the first time boot up configuration is FXO LS 4 For a full size FXO connect a test cable from a telephone CO switch or telephone line simulator to one of the TIP RING pairs on the rear connec tor...

Страница 7: ...st Step Action System Response 1 Make sure that the ICB is turned up and operating 2 Insert the DSU card into the appropriate slot of the ICB 3 Enable the NMS or craft interface and verify the chassis...

Страница 8: ...loopback menu listed under T1 settings for VT100 craft ter minal perform an OCU near end latching loop back with 2047 test pattern enabled Display should show Map 1 with zero bit errors Loopback LED t...

Страница 9: ...enter admin 11 Enter the following ip ping 192 168 0 1 Verify that the ping is returned 8 TECHNICAL ASSISTANCE If technical assistance is required contact Charles Industries Technical Services Center...

Отзывы: