360-80 Intelligent Channel Bank Turn-Up and

Acceptance Test Procedure

CONTENTS

PAGE

Part 1. GENERAL

2

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Part 2. VERIFYING ELECTRICAL CONNECTIONS

2

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Part 3. SYSTEM TURN-UP

2

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Part 4. CONTROL VERIFICATION

3

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Part 5. VERIFYING SYSTEM ALARMS

5

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Part 6. VOICE CARD ACCEPTANCE TESTS

5

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Part 7. DATA CARD ACCEPTANCE TESTS

7

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Part 8. TECHNICAL ASSISTANCE

9

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Содержание 360-80

Страница 1: ...echnical specifications herein subject to change without notice Page 1 of 9 360 80 Intelligent Channel Bank Turn Up and Acceptance Test Procedure CONTENTS PAGE Part 1 GENERAL 2 Part 2 VERIFYING ELECTR...

Страница 2: ...the Shelf documentation for the proper procedure Figure 1 displays the shelf rear panel 2 Apply power to the shelf 3 Locate the power terminal block on the rear see Figure 1 of the ICB Using a voltmet...

Страница 3: ...ID PWR Figure 2 T1 Controller Unit Front Panel 4 CONTROL VERIFICATION To get the information displayed as shown the control verification tests should be done with alarms active Control verification is...

Страница 4: ...th the NMS software installed con nect the ethernet from the PC to the network con trol terminal J2 on the rear of the T1 S 3 Activate the NMS software on the PC The NMS may start with the window mini...

Страница 5: ...rms exist 2 Release the T1 loopback Verify that there are visual and audible alarms 3 View the alarm status on the craft terminal and or NMS Display should show the correct alarm status 4 Press the AC...

Страница 6: ...nd the first time boot up configuration is FXO LS 4 For a full size FXO connect a test cable from a telephone CO switch or telephone line simulator to one of the TIP RING pairs on the rear connec tor...

Страница 7: ...st Step Action System Response 1 Make sure that the ICB is turned up and operating 2 Insert the DSU card into the appropriate slot of the ICB 3 Enable the NMS or craft interface and verify the chassis...

Страница 8: ...loopback menu listed under T1 settings for VT100 craft ter minal perform an OCU near end latching loop back with 2047 test pattern enabled Display should show Map 1 with zero bit errors Loopback LED t...

Страница 9: ...enter admin 11 Enter the following ip ping 192 168 0 1 Verify that the ping is returned 8 TECHNICAL ASSISTANCE If technical assistance is required contact Charles Industries Technical Services Center...

Отзывы: