The mounting instructions are described for a new installation. If the kits are supposed to be installed on an
already installed subsystem, you will have to release the water pressure and disconnect the electrical power
supply before starting. The installation must be carried out by a fully qualified electrician.
12.1 3-point HB metering
Mounting the 3-point HB metering:
1. Close the shut-off valves for primary inlet and return.
2. Unscrew the nut preceding the energy meter and remove energy meter and pipe.
3. Unscrew the nut following primary inlet and remove the filter and welding end.
4. Thread the metering profile into the frame´s.
5. Screw the metering and the central together.
6. Open the shut-off valves, first primary inlet then primary return.
Picture 28
12.2 Mounting floor stand
1. Mount two floor supports to the central. Use the outer mounting holes.
2. Mount the floor stand feet on the floor support.
3. Raise the central against a wall.
4. We recommend that the central is mounted to the wall.
The distance between floor and screw bracket should be 1330 mm. Note that distance between screws
are 400 mm.