CDL Maple Sugaring Equipment inc.
INSTALLATION OF THE ARCH
If your building is not insulated, you will have good combustion and a better evacuation of the
steam. However, if it’s well insulated, make sure you have enough fresh air intake to have a
good combustion and enough draft.
1. Remove the wheels under the evaporator.
2. Remove the pans. Level the arch using the adjustable legs.
3. When the evaporator is leveled, tighten the nuts on the legs.
4. The 2’ wide Venturi evaporator has a fixed Venturi system on the smoke stack.
It only requires a 110 volt plug in.
5. All the Venturi evaporators, 2-1/2’ and wider have a Venturi system that can be installed
remotely to lower the noise level. You just have to install an adaptor and enough pipe to
hook up the blower to the smoke stack. Try to minimize air flow restriction by installing the
blower as close as possible to the evaporator and by using long radius elbows if necessary.
6. The Venturi system must be hooked up in the first section of smoke stake on top of the base
stack.