62-10327
18
OPERATIONAL INSPECTION
on page 2 before proceeding.
1. Remove the Lock Out/Tag Out device and plug unit in to power
supply. Check that voltage is good on all 3 phases.
2. Install the manifold gauge set using good system hygiene practices.
For PrimeLINE units, operating pressures can be viewed by going to
code 12 (Suction Pressure) and code 14 (Discharge Pressure).
3. Turn unit power on and change the set point to 32ºF (0ºC). Check
Container ID on start up to ensure correct set up and also verify the
date and time is set to GMT. Check that the correct software and
configuration are loaded in the MicroLink controller on start up or
check at codes 18 and 20.
Note
: It is recommended to have
always the latest operational software loaded in the controller.
4. Check the condenser and both evaporator fans for proper rotation
(Refer to
).
Figure 22 Evaporator and Condenser Fans Proper Rotation
Содержание PrimeLINE 69NT40-561
Страница 2: ......
Страница 4: ......
Страница 8: ...62 10327 4 Figure 3 Evaporator Coil Figure 4 Evaporator Fan Blade...
Страница 11: ...7 62 10327 Figure 9 ETS1 and ETS2 Figure 7 TXV Figure 8 EEV...
Страница 17: ...13 62 10327 Figure 15 Flat Condenser Coil Figure 16 C Condenser Coil Flat condenser coil C condenser coil...
Страница 26: ......
Страница 28: ......
Страница 29: ......