Installation
Receiving the Machine
Inspect Shipment
1. Inspect for shipping damage while machine is still on shipping conveyance. If machine
appears to be damaged or has been torn loose from its anchorage, have it examined by
transportation inspectors before removal. Forward claim papers directly to transportation
company.
Manufacturer is not responsible for any damage incurred in transit.
2. Check all items against shipping list. Immediately notify the nearest Carrier representative if
any item is missing.
3. To prevent loss or damage, leave all parts in original packages until beginning installation.
All openings are closed with covers or plugs to prevent dirt and debris from entering
CAUTION
CAUTION
!
Do not open any valves or loosen any connections. The 19FA machine may be
shipped with the entire refrigerant charge in the storage tank and a small refrig-
erant holding charge in the cooler and condenser. Some machines may be
shipped with a nitrogen holding charge in the machine and the refrigerant
shipped separately.
Содержание HFC-134a
Страница 30: ...Click here for Figure 20 Pumpout Unit Controls Click here for Figure 21 Pumpout Unit Wiring Schematic ...
Страница 40: ...Figure 1 Model Number Identification ...
Страница 41: ...Figure 2 Typical 19FA Installation 1400 2200 Tons 4922 7735 kW ...
Страница 42: ...Figure 3 Machine Rigging Guide 3 Indicates center of gravity ...
Страница 44: ...Figure 5 Machine Footprint ...
Страница 45: ...Figure 6 Machine Contact Surfaces with Anchor Bolts ...
Страница 51: ...Figure 12 Water Piping Oil Cooler to Chilled Water Circuit Typical ...
Страница 52: ...Figure 13 Pumpout Unit ...
Страница 53: ...Figure 14 Typical 19FA Relief Valve Tree for Storage Vessel ...
Страница 54: ...Figure 15 Compressor Terminal Arrangement 18 Lead Rear Inlet ...
Страница 55: ...Figure 16 Compressor Terminal Arrangement 18 Lead Top Inlet ...
Страница 56: ...Figure 17 Compressor Terminal Arrangement 18 Lead Side Inlet ...
Страница 57: ...Figure 18 Oil Pump Wiring ...
Страница 58: ...Figure 19 Oil Heater and Control Power Wiring ...
Страница 59: ...Figure 20 Pumpout Unit Controls ...
Страница 60: ...Figure 21 Pumpout Unit Wiring Schematic ...
Страница 61: ...Figure 22 Carrier Comfort Network Communication Bus Wiring ...
Страница 62: ...Figure 23 COMM1 CCN Communication Wiring For Multiple Chillers Typical ...
Страница 63: ...Figure 24 Typical 19FA With Free Standing Starter ...
Страница 64: ...Figure 25 Field Wiring Low Voltage Motors of PIC Product Integrated Control Free Standing Starter ...
Страница 65: ...Figure 26 19FA Insulation ...