INITIAL SOLUTION AND
REFRIGERANT CHARGING
Lithium bromide solution and refrigerant (water) will be
placed in the chiller at initial start-up. Do not charge solu-
tion into chiller until the unit is ready for operation.
Do not start any pump motors until the chiller has been
charged with solution and refrigerant. The hermetic pumps
can be seriously damaged by dry operation.
See 16JT Start-Up, Operation, and Maintenance instruc-
tions for charging procedures.