10.1 Maintenance
Maintenance interventions on the humidifi er should be carried out by
specifi cally qualifi ed staff .
Important
:
before proceeding with any operation:
•
cut off the power supply setting the master switch of the machine to
“OFF”;
•
close the shut-off valve of the water supply line.
•
ON/OFF swithc on the device cuts off power to electronic circuit only,
not to heaters!
10.2 Maintenance operations
Routine maintenance of humidifi ers using tap water provides:
1.
cleaning all the parts that come into contact with water:
a.
feeding solenoid valve;
b.
loading/unloading group:
c.
drain pump;
d.
heaters;
e.
collection tray with lime collection basket (models UR002-
UR013);
2.
boiler gasket replacement.
Non-routine maintenance is carried upon every time scheduled
maintenance request (code “CL” on display). Therefore, it is necessary to
perform complete maintenance of the humidifi er and reset the hour
counter.
10.3 Maintenance frequency
Maintenance frequency depends on the amount of water and steam
generated.
Tap water
Water hardness
15…25 °f
25…40 °f
Daily operating hours
8…10
8…10
No. of maintenance/ year
2
3
Tab. 10.h
Demineralised water
The use of demineralised water minimises maintenances times.
Note
: we recommend you carry out non/routine maintenance at
least once a year, regardless of the operating hours and the data
shown on the hour counter.
10.4 Maintenance of the cylinder-boiler
This operation is necessary as the lime deposits that form inhibit the
exchange of heat between the heating elements and the water.
Warning
:
•
do not use detergents or solvents to clean the components in the
boiler and all other plumbing;
•
do not use metal devices to clean the heating elements;
•
the boiler may be hot! Wait for the boiler to cool down before touching
it or use safety gloves.
To access the boiler:
•
shut down the device and open the breaker of the power supply line;
•
completely empty the boiler from water (see the “Shutdown” section);
•
open and remove the front panel (see chapt. 1).
Models UR002-UR013
(refer to the following fi gures):
!
drain
x 1000
Steam
Drain
Fill
Alarm
PRG
reset
SEL
I
8
7
2
3
4
9
5
1
Fig. 10.f
1.
loosen the seal strip and remove the steam pipe (1);
2.
disconnect level gauge connector (2);
3.
remove the pressure regulation pipe (3), connected to the level
gauge, from boiler cover
4.
loosen te fastening clamp (4) and incline the boiler outwards.
5.
remove the cover that protects the heaters (5), loosen the fastening
nuts and remove the wires. Remove the ground cable screw as well
(7);
6.
disconnect the probe connector and remove the NTC probe from
the well (8);
7.
remove the boiler. Place it on a fl at surface resistant to water and
limestone that may come out during cleaning;
8.
cylinder opening; loosen the screw and open the ring nut;
9.
lift the cover to which are fastened the heaters and remove it from
the cylinder;
D
Fig. 10.g
10.
remove the spacer (D);
11.
to replace the heaters refer to the next section;
12.
clean the heaters (see the next section);
13.
remove the lime collection basket from the bottom of the cylinder:
rinse it and clean it with a soft brush;