Alternatively, a more accurate correction factor for the 
open-circuit voltage can be calculated using the following 
formula:

T  (°C) is the lowest expected ambient temperature at the 
system installation site

α

Voc

 (%/ºC) is the voltage temperature coefficient of the 

selected module (refer to corresponding datasheet)

OCPD rating selection should be done per the following 
guidance, where the minimum OCPD rating possible is 
determined by calculating the expected maximum cir-
cuit current for the PV system, and the maximum OCPD 
rating constrained by the IEC 61215: 2016 and UL 1703: 
2018 standard requirements for the certified PV modu-
les.

   Minimum string fuse rating  < X ≤ Maximum string fuse 

rating

The maximum string fuse ratings can be found in ANNEX 
A: Mechanical And Electrical Ratings for all the certified 
Canadian Solar bifacial module types.

The minimum string fuse rating for compliance with 
NEC: 2017 code and IEC62548: 2016 requirement is sug-
gested to be determined as follows:

   Minimum string fuse rating = IscSTC x 1.25 x Max (1.175, 

Imppα ÷ ImppSTC)

   Imppα = the highest 3-hour current average resulting 

from the simulated local simultaneous irradiances on 
the front and rear sides of the PV array accounting for 
elevation and orientation

   IscSTC = the listed short circuit current at 0% bifacial 

gain on the PV module datasheet or nameplate label

   ImppSTC = the listed MPP operating current at 0% bi-

facial gain on the PV module datasheet or nameplate 
label

An assembly, together with its overcurrent device (s), 
that is listed for continuous operation at 100 percent of 
its rating shall be permitted to be used at 100 percent of 
its rating, and therefore shall not require the additional 
1.25 multiplier

C

VOC 

= 1-α

Voc

  ˣ (25 - T)

Appropriate correction factors should be selected by 
licensed professional electrical engineers according to 
relevant design codes and system simulation results. 
Canadian Solar does not take responsibility for the deter-
mination of the minimum series fuse rating.

4.0  

UNPACKING AND STORAGE

PRECAUTIONS 

·  Modules should be stored in a dry and ventilated en-

vironment to avoid direct sunlight and moisture. If 
modules are stored in an uncontrolled environment, 
the storage time should be less than 3 months and ex-
tra precautions should be taken to prevent connectors 
from being exposed to moisture or sunlight, like using 
connector endcaps. Specific T4 connector endcaps are 
available upon request.

· 

Unpack module pallets carefully, following the steps 

shown on the pallet. Unpack, transport and store the 
modules with care.

· 

Modules must always be unpacked and installed by 

two people. Always use both hands when handling 
modules. 

·  

Do not 

lift modules by their wires or junction box. 

·  

Do not 

stack the frameless and framed modules. 

·  

Do not 

place excessive loads on the module or twist 

the module. 

·  

Do not 

stand, step, walk and/or jump on modules 

under any circumstances. Localized heavy loads may 
cause severe micro-cracks at cell level, which in turn 
may compromise module reliability and void Canadian 
Solar Inc’s warranty. 

Содержание CS3U-MB-FG

Страница 1: ...1 INSTALLATION MANUAL OF BIFACIAL MODULE For professional use only...

Страница 2: ...NTING METHODS FOR FRAMELESS BIFACIAL MODULE CLAMPING 12 6 2MOUNTING METHODS FOR FRAMELESS BIFACIAL MODULE SINGLE AXIS TRACKERS 14 6 3 MOUNTING METHODS FOR FRAMED BIFACIAL MODULE BOLTING 15 6 4 MOUNTIN...

Страница 3: ...to property in connection with handling PV modules system installation or compliance or non compliance with the instructions set forth in this manual 2 0 SAFETY PRECAUTIONS Warning Before attempting t...

Страница 4: ...e fer tility or the unborn child causes damage to organs through prolonged or repeated exposure is very toxic to aquatic life with long lasting effects may cause cancer is very toxic to aquatic life a...

Страница 5: ...V module datasheet or nameplate label An assembly together with its overcurrent device s that is listed for continuous operation at 100 percent of its rating shall be permitted to be used at 100 perce...

Страница 6: ...ding to IEC 61730 2 please refer to the datasheet or the product nameplate for the detailed types Consult your local authority for guidelines and require ments for building or structural fire safety U...

Страница 7: ...uld be safely fixed to bear all expected loads including wind and snow loads After the installation of double glass modules a maximum 40 mm deflection for frameless module and a 30 mm deflection for f...

Страница 8: ...ort circuit current Isc differ substantially from the spe cifications this indicates that there is a wiring fault Do not connect different connectors brand and model together When modules have been pr...

Страница 9: ...400 mm 280 mm 1400 mm jumper cable Modules in adjacent rows should be rotated 180 degrees for proper installation Portrait installation one row Leap frog for single axis tracker CS3U Cable length 167...

Страница 10: ...sible to use standard grounding methods for certain module ranges CORRECT CONNECTION OF PLUG CONNECTORS Make sure that all connections are safe and properly mated The PV connectors should not be subje...

Страница 11: ...e cup washer concave side up between the frame and the wire 2 Then tighten the bolt using the toothed nut GROUNDING METHOD BOLT TOOTHED NUT CUP WASHER and UL 1703 a safety factor of 1 5 should be appl...

Страница 12: ...t shadow on the cells 3 Not to damage or scratch the surface of the glass 4 To ensure the clamps overlap the module by 13 mm to 15 mm 5 To ensure the minimum clamping clearance of the clamps 4 mm 6 To...

Страница 13: ...20 mm Maximum Load Uplift load 2400 Pa Downforce load 3600 Pa Use 6 clamps on the long side Mounting rails run parallel to the long side frame Use 4 clamps on the long side Mounting rails run perpend...

Страница 14: ...0 Pa Clamp length 200 mm A 390 20 mm Maximum Load Uplift load 2400 Pa Downforce load 5400 Pa 6 2 MOUNTING METHODS FOR FRAMELESS BIFACIAL MODULE SINGLE AXIS TRACKERS These mounting methods have been qu...

Страница 15: ...Clamp A A A A A A A A Tube Clamp Rail Clamp A A A A Tube Rail A A Use 4 clamps on the long side Mounting rails run parallel to the long side frame Mounting rails fixed on torque tube Clamp length 130...

Страница 16: ...nal mounting points should be used The system designer and the in staller are responsible for calculating the load and ensu ring that the support structure meets the requirements Modules should be bol...

Страница 17: ...limit as much as possible shade on module rear side cells Canadian Solar Inc s warranty may be void in cases where improper clamps or unsuitable installation methods are found When installing inter m...

Страница 18: ...s run perpendicular to the long side fra me Clamp length 40 mm A 270 380 mm C 10 2 mm Maximum Load Uplift load 2400 Pa Downforce load 3600 Pa Clamp length 80mm A 270 380 mm Maximum Load Uplift load 36...

Страница 19: ...Mounting rails fixed on torque tube tracker Two modules share one tube portrait installation Bolting on long frame side using 400 mm 1300 mm mounting holes as shown at arrow location Mounting rails ru...

Страница 20: ...rce load 2400 Pa A A Mounting Rail Clamp Use 2 long center clamps on the long side of each module or bolting on the center holes of the long side frame Overlap length of clamp and frame 400 mm Maximum...

Страница 21: ...st mounting holes Mounting rails run parallel to the long side frame Mounting rails fixed on torque tube tracker Overlap support length of between rail and frame A 730 mm Center distance between clamp...

Страница 22: ...M6 plain washer O D 18 mm 1300 mm 400 mm holes position Drawing No SF7 MR 04 039_Drbiku 1800Pa 30mm Uplift load 1800 Pa Downforce load 1800 Pa SF7QG 1500V en revision 1 0 CS3U MB AG CS3U PB AG Soltec...

Страница 23: ...uire cleaning rain will have a self cleaning effect If the module has become soiled it shall be washed with water and a non abrasive cleaning brush or sponge du ring the cool part of the day Do not sc...

Страница 24: ...and corner protector 24 3 kg 53 6 lbs CS3K 285MB FG 285 31 9 8 94 38 7 9 57 25 CS3K 290MB FG 290 32 1 9 04 38 9 9 65 25 CS3K 295MB FG 295 32 3 9 14 39 1 9 73 25 CS3K 300MB FG 300 32 5 9 24 39 3 9 82 2...

Страница 25: ...310PB FG 310 33 1 9 37 39 7 9 81 25 CS3K 315PB FG 315 33 3 9 46 39 9 9 89 25 CS3K 320PB FG 320 33 5 9 56 40 1 9 97 25 CS3K 325PB FG 325 33 7 9 65 40 9 10 21 25 CS3U 350PB AG 350 39 2 8 94 46 6 9 51 2...

Страница 26: ...ent Imp A Open Circuit Voltage Voc V Short Circuit Current Isc A Max Series Fuse Rating A Overall Dimension mm Weight Kg CS3W 420PB AG 420 39 5 10 64 48 0 11 26 25 CS3W 425PB AG 425 39 7 10 71 48 2 11...

Страница 27: ...covers the requirements for the cleaning pro cedure of Canadian Solar Inc s photovoltaic modules The purpose of these cleaning guidelines is to provide general information for cleaning Canadian Solar...

Страница 28: ...re that brushes or agitating tools are not abrasive to glass EPDM silicone aluminum or steel Conduct the cleaning activities avoiding the hottest hours of the day in order to avoid thermal stress on t...

Отзывы: