1. Visual Inspection Of Equipment
(page 28)
2. Electrical Supply Voltage Verification
(page 28)
3. Gas Supply Pressure Verification
(page 29)
4. Blower Rotation Check
(page 29)
5. Burner Profile Damper Pressure Drop Check
(page 29)
6. Motor Amp Draw Check
(page 30)
7. Calculating and Adjusting
Burner Manifold Pressure
(page 30)
8. Gas Valve Leak Check
(page 31)
9. Gas Train Leak Check
(page 32)
10. Minimum Fire Setting
(page 32)
11. Low Fire Start Adjustment
(page 33)
12. Preliminary Remote Control Station
Operational Check
(page 33)
13. Final Heater Preparation
(page 34)
14. Final Remote Control Station Check
(page 34)
After start-up, please complete and fax the M-Series
Start Up Checklist to the Cambridge Customer Service
Group. Receipt of a completed checklist will extend
the start date for your warranty period to the date of the
start-up but not to exceed six months from date of ship-
ment.
IMPORTANT
Read the following instructions carefully. Any
unauthorized modifications to, or deviations
from these instructions may void the warranty.
1. VISUAL INSPECTION OF EQUIPMENT
a. Check for any physical damage from ship-
ping or installation that could render the heater
inoperable.
b. Verify all heater accessories and filters (if
applicable) have been properly installed.
c. Check for loose components (belts, plugs, ter-
minal screws, etc.).
d. Verify the access doors and controls enclosure
are free from obstructions, such that they can
be fully opened.
e. Verify the field wiring, both primary and
control, has been installed according to the
Cambridge Engineering wiring diagram and
the National Electrical Code.
f. Verify that a sediment trap has been provided
upstream of other gas train components.
g. Verify the high pressure regulator and/or vent
valve, if applicable, have been vented to the
outside of the building at least 10 feet from
any intake opening or 4 feet above the heater.
h. Verify the factory supplied manual gas shut-
off cock is installed external to the heater and
downstream of the high pressure regulator, if
applicable.
i. Verify that the gas piping unions are tight.
j. Verify that the burner union is tight.
2. ELECTRICAL SUPPLY VOLTAGE
VERIFICATION
For model M110 - M115 heaters, remove electri-
cal enclosure access door and check the electrical
supply voltage at the terminal block provided off