Hex nut
Spring shim
Washer
Expansion bolt
Install four expansion bolts into the
rough-in base and tighten hex nuts.
Teflon Tape
Hot feeding pipe
Cold feeding pipe
Wrap the coupling with
Teflon tape and connect
it to the rough-in base.
Then connect inlet pipes
of proper length.
Towards bathtub
Insert expansion bolts into
Ø8
holes.
(Attention
the “HOT” mark on the
rough-in base is the hot water inlet
should face towards the bathtub
)
Level
Level
M8 Screw
Adjust M8 screws on the rough-in
base to its level position. When
bubbles inside the level are in the
center of the circle, the rough-in
base is at level position, and then
tighten hex nuts.
Rough-in box
Silicone sealant
Fill silicone sealant in between
the rough-in box and finish
floor such as tiles.
Reference of
finished floor
For floor work, make sure the center of
inlet pipes to finished floor is between
28-50mm.
Cover
Remove the cover and run
water for pressure test.
Check all joints to make
sure no leakage. Then put
back the cover.
Hot feeding pipe
Cold feeding pipe
Flush W
ater
Flush W
ater
Run water to get rid
of any debris inside
pipes. Connect cold
and hot water pipes.
Attention that the
HOT mark is to the
hot water pipe and
COLD mark to the
cold pipe.