SERVICE (cont.)

Off/On/Start Switch

Location:

The Off/On/Start switch is centered in the hous-

ing above the upper front inspection panel.

Test Procedure:
1.

Disconnect the grinder from the power supply.

2.

Remove the black wire from the switch.

3.

Check for continuity across the black wire from
the Off/On/Start switch and the left blade of the
cordset connector (see illustration below).

If continuity is present as described, proceed to

step 4.

If continuity is not present as described, refer

to the Wiring Diagrams and check the grinder wiring
harness.

4.

Remove the remaining wires from the switch.

5.

Check for continuity across the lower terminals
when the switch is placed in both the “ON” (cen-
ter) and “START” (right) positions.

If continuity is present as described, proceed to

step 6.

If continuity is not present as described, replace

the switch.
6.

Check for continuity across the upper terminals
when the switch is placed in the “START” (right)
position only.

If continuity is present as described, the Off/On/

Start switch is operating properly.

If continuity is not present as described, replace

the switch.

Removal and Replacement:
1.

Remove all wires from the switch terminals.

2.

Compress the clips inside the front wrapper and
gently push the switch through the opening.

3.

Push the new switch into the opening and spread
the clips to hold the switch captive in the hood.

4.

Refer to the illustration below when reconnect-
ing the wires.

Urn/Carafe Switch

Location:

The Urn/Carafe switch is located to the left side

on the front of the housing above the upper inspec-
tion panel.

Test Procedure:
1.

Disconnect the grinder from the power supply.

2.

Remove the tan, yellow and green wires from
the switch.

3.

Place the switch in the “CARAFE” position; check
for continuity across the pink and the tan wire
terminals, also across the orange and the yel-
low wire terminals.

If continuity is present as described in both

checks, proceed to step 4.

If continuity is not present as described in one

or both of the checks, replace the switch.

4.

Place the switch in the “URN” position; check
for continuity across the orange and green wire
terminals.

If continuity is present as described, the switch

is operating properly.

P606

WHI/YEL to Timer TL5

WHI/ORA to Timer TL3

BLK to Cordset

WHI/RED to Timer TL1

P1300

CORDSET CONNECTOR

Looking Strait-on

Black

Ground

White

10171 041597

Содержание G9 HD

Страница 1: ...FAX 217 529 6644 10171 0000 5 00 1986 Bunn O Matic Corporation BUNN G9 HD G9T HD PE RS ON AL IN JU RY HA ZA RD KE EP FIN GE RS AN D FO RE IG N OB JE CT S OU T OF HO PP ER OR CH UT E OP EN ING CAUTIO...

Страница 2: ...d by Bunn or that in Bunn s judgement has been affected by misuse neglect alteration improper installation or operation improper mainte nance or repair damage or casualty THE FOREGOING WARRANTY IS EXC...

Страница 3: ...e entrance to the grind chamber 2 Fill hopper compartment with whole bean coffee Capacity 9 pounds The grinder is now ready for use OPERATING CONTROLS Off On Start Switch OFF left position Placing the...

Страница 4: ...can be set from very fine to very coarse The amount may be adjusted for use in most commercial coffee brewers The following procedures should be used to make adjustments A change in the burr adjustmen...

Страница 5: ...cover Timer Adjustment NOTE Grinders with Multi Set option Urn Carafe must be adjusted in both settings 1 Unplug the grinder and remove the lower front inspection panel 2 Determine the grind setting...

Страница 6: ...aution when servicing electrical equipment Turn power OFF when servicing except when electrical tests are specified Follow recommended service procedures Replace all protective shields or safety notic...

Страница 7: ...dures See page 12 Refer to Service Motor for testing procedures See page 9 A Place the switch in the OFF left position B Refer to Service Off On Start Switch for testing procedures See page 11 Refer t...

Страница 8: ...id removal The rear panel is attached with eight 8 32 screws The hopper extension assembly is attached with six 8 32 screws Contents Motor 9 Off On Start Switch 11 Urn Caraffe Switch 11 Relay 12 Timer...

Страница 9: ...plate 2 The entire wiring harness must be fed into the bottom of the grinder housing through the hole in the motor mounting plate 3 Remove both 6 32 screws beneath the upper front inspection panel 4...

Страница 10: ...amaged NOTE Burrs must be replaced as a set SERVICE cont Motor cont 11191 0001 COARSE FINE T H O R O U G HLYCLEAN GRIND CHAM B E R B E F O R E R E A S S E M B L Y E M P T YHOPPER BEFORE REM O V IN G T...

Страница 11: ...cribed replace the switch Removal and Replacement 1 Remove all wires from the switch terminals 2 Compress the clips inside the front wrapper and gently push the switch through the opening 3 Push the n...

Страница 12: ...START right position and released Connect grinder to the power supply Continuity must be present for the approximate setting on the timer 6 Disconnect the grinder from the power supply If continuity...

Страница 13: ...rness 6 Check the voltage across terminals TL1 and TL4 with a voltmeter when the Off On Start switch is placed in the START right position and re leased Connect grinder to the power supply The indicat...

Страница 14: ...WHI WHI WHI RED WHI RED OPTIONAL KEY SW 5 4 3 2 1 W H I O R A ORA URN CARAFE WHI GRN 1 BLK K1 WHI BLU M L2 L1 120 VOLTS AC 2 WIRE SINGLE PHASE 60 HZ 10215 0000C 4 97 1987 BUNN O MATIC CORPORATION L1 N...

Страница 15: ...HD TIMER WHI RED WHI YEL WHI ORA RED BLK RED BLK WHI RED WHI RED 5 4 3 2 1 10187 0001B 11 97 1997 BUNN O MATIC CORPORATION WHI GRN BLK K1 WHI BLU M L2 L1 200 VOLTS AC 2 WIRE SINGLE PHASE 50 HZ L1 L2...

Страница 16: ...RED GRY 1 2 OPTIONAL MULTI SET SW OPTIONAL BREWER INTERFACE CONNECTOR PNK TAN ORA PNK OPTIONAL KEY SW W H I O R A K1 M 120 VOLTS AC 2 WIRE SINGLE PHASE 60 HZ 4 3 WHI GRN 1 BLK WHI BLU M L2 L1 10388 0...

Отзывы: