Step #1:
Position the side sills with the inside up on a
protected at surface. Loosely attach the cross support
brackets to each side sill using 5/16-18 x 2” hex head cap
screws and 5/16 washers.
Step #2:
Assure that the cleats are perpendiculiar to the
top of the sill and securly tighten.
FIGURE ONE
FIGURE TWO
Step #3:
Place one end sill into position by sliding the
hex head screws through the clearance holes of the sill
cleats and secure with 3/8-16 threaded nut within the leg
as shown.
Step #4:
Continue attaching both end sill and two side
sills.
FIGURE THREE
FIGURE THREE
Step #5:
Set the cross supports into position. Make sure
that they do not set above the side sill. It may require
shaving wood off the bottom of the cross support.
Step #6:
Loosely attach the cross supports with 3/8-16 x
3-1/4” hex head cap screws, two 3/8 washers and
3/8-16 hex nuts.
Step #7
: Position the baseframe in it permanent
location with sides and ends at least 60” away from
walls or obstructions.
Step #8:
Square the table by measuring diagonally,
adjust if necessary by pushing at the of the baseframe
diagonally until measurements are within 1/8”.
Step #9:
Tighten all hardware securely
FIGURE TWO