Installation and Operation Manual
X-PR-IPS122-eng
Part Number 541B150AAG
January, 2011
2-2
Section 2 Installation
IPS122 Series
2-4 Return Shipment
Prior to returning any device to the factory, visit the Brooks web site
(www.BrooksInstrument.com) for a Return Materials Authorization Number
(RMA#), or contact one of the locations provided on p. 2-1.
Prior to returning the device, it must be purged in accordance with the
following:
All devices returned to Brooks require completion of Form RPR003-1, Brooks
Instrument Decontamination Statement, along with a Material Safety Data
Sheet (MSDS) for the fluid(s) used in the instrument. Failure to provide this
information will delay processing by Brooks personnel. Copies of these forms
can be downloaded from the Brooks website (www.BrooksInstrument.com) or
are available from any of the Brooks Instrument locations provided on p. 2-1.
2-5 Transit Precautions
To safeguard against damage during transit, transport the device to the
installation site in the same container used for transportation from the factory,
if circumstances permit.
2-6 Removal from Storage
Upon removal of the device from storage, a visual inspection should be
conducted to verify its "as-received" condition. If the device has been subject
to storage conditions in excess of those recommended (refer to "2-3
Recommended Storage Practice" on p. 2-1), it should be subjected to a
pneumatic pressure test in accordance with applicable vessel codes.
2-7 Gas Connections
Prior to installation, ensure that all piping is clean and free from obstructions.
Install piping in such a manner that permits easy access to the device if
removal becomes necessary.