In some instances consideration is given to the possibility that, due to circumstances, there is a possibility that a
“minor“ incident, due to complications may escalate into a “serious” or even “disasterous” injury.
The Risk level score calculation is shown included in column 3 of the Risk Asessment.
RISK SCORE CALCULATIONS
The risk score is a factored in the following order:
Consequence (1 to 6)
1 being lowest consequence
Probablility (1 to 6)
1 being lowest probability
Exposure (1 to 6)
1 being lowest exposure
Below is an example of the method used to calculate the risk scores with the aid of the Matrices.
Sample: Risk Assessment table excerpt.
Hazard
Risk
Score
Control
Recommendation
Action Taken
Yes / No
Re-
Score
Rotating blade in reach of
operator at normal work station
of shift.
Severing injury risks
R
ISK
S
CORE
:
6:5:4
V
•
Consequence
Very Serious
4
•
(Permanent disability, loss to
$1,000,000 )
•
Probability
Quite Possible
5
Quite possible
•
Exposure
Frequent
5
Frequent
•
Code
V
The risk score calculation shall be indicated as follows 4:5:5= V
Code
Risk Level
Suggested action
V
Very High
Immediate cessation of work, isolation of area and corrective action required
H
High
Immediate corrective action required
S
Substantial
Should receive attention within specified time
M
Moderate
Should be dealt with within specified time but not an emergency
L
Low
Risk is acceptable