Commissioning - Testing the System

With the front cover removed ensure the black ‘purge/shower’ 

switch inside the base is switched to purge. This enables water to 

flow without the pump running which is necessary in the following 

commissioning process.

Fit the front cover using the 3 fixing screws.

Push the temperature control knob onto the spindle with the marker 

pointing to the ‘12 o’clock’ position.

Connect the shower hose to the unit but do not fit the handset.

Turn on the hot and cold isolating valves, and the electricity-isolating 

switch. Place the open end of the hose in the bath or shower tray.

Set the temperature control knob to fully cold (marker at ‘6 o’clock’ 

position) and press the ‘stop/start’ button. The pump will not operate 

but the water should run.

Cold water will run from the hose, and you should allow this to 

continue for two minutes after which the control knob should be 

returned to the ‘12 o’clock’ position. Allow the water to run for a few 

minutes to stabilise the hot water flow.

Turn off the electricity at the isolating switch and remove the knob 

and cover. Switch the black ‘purge/shower’ switch to shower and refit 

the cover and knob ensuring the marker on the knob points to the ‘12 

o’clock’ position.

Turn on the electricity at the isolating switch.

Pass the hose through the hole in the front of the soap dish and refit 

the handset. 

Your shower is now ready to run. Press the stop/start button on the 

front cover to operate the shower, which will work  as a power shower. 

It is intended that the temperature knob aligned to the ‘12 o’clock’ 

position you should get  a comfortable shower temperature. If 

however the shower is too hot or cold remove the control knob and 

adjust the brass spindle anti-clockwise to increase the temperature 

- clockwise to decrease. When the desired shower temperature is 

achieved replace the knob with the marker pointing to the ‘12 o’clock’ 
position.  

 

Temperature Adjustment

The valve allows the maximum showering temperature to be set at a 

safe level, preventing accidental scalding. This setting should be made 

during commissioning and will require that the hot water cylinder is at 

its normal operating temperature.

IMPORTANT:

The handset must be in the spray mode.

We recommend the reading of User Instructions before proceeding 

further. This will familiarise you with the operation of the shower.

Turn the brass mixer valve spindle fully clockwise, and then anti-

clockwise until the black line on the spindle  is aligned with the groove 

on the mixer body, and fit the control knob in the fully cold position. 

Check that it is correctly fitted by turning fully clockwise to the stop, 

pull the knob off and check that the black line and groove are aligned. 

Adjust if necessary. This sets the shower temperature to 38-40°C, with 

the control knob pointing to ‘12 o’clock’, if the stored hot water is at 

the recommended 60°C.

HOT

COLD

PURGE

SHOWER

Need help?

 Give us a call on

 0844 701 6273

 and speak to one of our trained advisors.  

Purge/shower Switch

Temperature adjustment

Содержание Thermostatic Power Shower 1000

Страница 1: ...ase keep this booklet for future reference Installer when you have read these instructions please ensure you leave them with the user Installation Instructions and User Guide Thermostatic Power Shower 1000 ...

Страница 2: ...g your shower 7 Fitting the riser rail 9 Commissioning testing the system 10 Operating the shower 11 Adjusting the showerhead 11 Cleaning maintenance 11 Troubleshooting 12 Spare parts 13 Guarantee 14 Service policy 14 Contents Need help Give us a call on 0844 701 6273 and speak to one of our trained advisors ...

Страница 3: ...g it smothering it on your hand or any other part of your body or foreign object Do not operate the shower if the water stops flowing during use or if the water is leaking from the shower unit itself General Safety Always switch off the power at the consumer unit and remove the correct circuit fuse before making any electrical connections or if you have to remove the cover of an installed unit The...

Страница 4: ... and control knob already in place These have to be removed to install the shower Please follow the procedure below Pull off control knob 1 Remove all three fixing screws 2 The cover can now be slowly removed care should be taken not to strain wiring which is attached to the front cover This procedure can be reversed to replace the front cover and control knob after installation to the wall Need h...

Страница 5: ...rrent I E E regulations As the colours of the wires in the cable not supplied used to connect to this appliance may not correspond with the coloured markings identifying the terminals in your switch please follow the procedure below Please use the cable entry point provided Failure to comply will eliminate any BEAB approval Procedure The wire which is coloured Blue or Black must be connected to th...

Страница 6: ...ing valves must be fitted on hot and cold supply pipes Do not position unit in areas subjected to freezing conditions The temperature of your stored water must not exceed 65 C A stored water temperature of 60 C is considered sufficient to meet all normal requirements in line with the British Standard 6700 Warning All connecting pipe work should be earthed Procedure Plumbing Connections Isolate mai...

Страница 7: ...ust be roughened or removed to ensure that the push fit fittings in the supply retain the pipe in position The inlet elbows supplied are of a standard length in some cases these will need to be shortened for correct installation Flush out the supply pipes to ensure that no debris enters the unit Cut the inlet elbows to the required length Locate the inlet elbows into the mixer valve inlets by push...

Страница 8: ...llow Green to the terminal marked E Secure into position with the cable clamp and tighten the two fixing screws Do not fit the front cover at this stage refer to the commissioning procedure Note If the electrical supply cable is concealed in the wall ensure that it avoids the unit s fixing points so that fixing screws do not pierce the cable HOT COLD Need help Give us a call on 0844 701 6273 and s...

Страница 9: ...ed fixing position using a 6mm drill to a depth of 35mm push the plugs 4 supplied into the hole and loosely fix the rail end using the screw supplied 5 checking that the rail is hanging vertically using the spirit level incorporated into the top end of the rail The bubble should be exactly between the two lines on the spirit level body Mark the position for the lower fixing screw move the rail to ...

Страница 10: ...he stop start button on the front cover to operate the shower which will work as a power shower It is intended that the temperature knob aligned to the 12 o clock position you should get a comfortable shower temperature If however the shower is too hot or cold remove the control knob and adjust the brass spindle anti clockwise to increase the temperature clockwise to decrease When the desired show...

Страница 11: ...g liquids powders or specified scratch cleaners on any surface finishes In order to avoid surface wear or chemical attack on any of your shower fittings when cleaning always use a damp cloth For persistent stains or marks you may use domestic liquid or soap Handset The Handset has three spray modes 1 Spray 2 Massage 3 Combination To select the desired showering mode grip the bezel of the handset a...

Страница 12: ... is flowing No electricity supply to unit Check all fuses and electrical supply Pump operates but no water is flowing No water supply to unit Check isolating valves are turned on Check cold water storage tank has not run dry Poor performance Restrictions in water supply Check both hot and cold isolating valves are fully open Pump may have overheated Allow unit to cool and retry Unit may be incorre...

Страница 13: ...ve assembly 1 08 SP 087 0211 Purge shower rocker switch 1 09 SP 087 0127 Pipe connection 1 10 SP 087 0110 Pump unit 1 11 SP 087 0068 Pipe cover 1 12 SP 086 0061 Long inlet elbow 2 13 SP 087 0035 Motor cover 1 14 SP 280 0024 Rail end cap 1 15 SP 280 0100 Spirit rail and slider assembly 1 16 SP 280 0033 Soap dish 1 17 SP 285 0820 Hose 1 18 SP 168 0204 Handshower 1 HOT COLD Need help Give us a call o...

Страница 14: ...maintained and operated in accordance with our instructions and has not been misused or damaged Modification or repair of this product by person s not authorised by Bristan will invalidate this guarantee This guarantee does not affect your statutory rights Service Policy Replacement Parts Policy Important In the event of product or component malfunction DO NOT tamper with or remove the product fro...

Страница 15: ...15 Need help Give us a call on 0844 701 6273 and speak to one of our trained advisors ...

Страница 16: ...Bristan Group Ltd Birch Coppice Business Park Dordon Tamworth Staffordshire B78 1SG Web www bristan com Email enquire bristan com A Masco Company Issue POW SHX 1000 D2 Part Number 131 723 ...

Отзывы: