BPW-EA-AS 37772001de
English
Seite 21
Commissioning
5
Checking the control unit outlet pressure
5.1
[2]
Connect pressure gauge to the test connection.
(Attention, pressure gauge is not included in the
scope of supply)!
[3] Open
shut-off valve on the AirSave Control Box
(842).
[4] Read
off the pressure on the pressure gauge when
the pumping process has ended.
Installation and repair guide!
Before commencing work on the system
or on the wheel ends, always close the
shut-off valve and relieve air on the excess
pressure valve.
The outlet pressure must be 0.1 to 0.2 bar
over the manufacturer's recommended tyre
pressure in order to equalise the opening
pressure of the downstream components.
The outlet pressure is preset (see AirSave Con-
trol Box cover plate) and must be checked before
commissioning.
[1]
Remove cap on the pressure connection (arrow,
Figure 15).
Figure 15
Figure 16
Shut-off valve
[5]
Remove pressure gauge.
[6]
Relieve pressure at the valve.
[7]
Wait for the AirSave Control Box pumping process
and then reassemble the pressure gauge.
[8]
Repeat the test procedure twice.
Warning:
Incorrectly set outlet pressures can lead
to tyre failure, increased tyre wear and
increased fuel consumption.
[9]
Remove pressure gauge and screw the cap onto
the valve.
Figure 17