14 | Installation
4
Installation
4 .1
Packaging and product identification
The SSB is delivered strapped to a pallet, packed and protected in a
cardboard carton.
NOTICE: The packaging shows the characteristics of the
product: model, power, fuel type and version. In case of
deviation from the order, contact your local dealer.
After removing the packaging check the condition and
completeness of delivery.
a
a
WARNING: Keep the packing material out of reach of
children as it may be dangerous.
Dispose of packaging in an environmentally responsible
manner.
a
m
In order to ensure proper product identification do not
remove or tamper with any product identification tags or
labels.
4 .2
Installation room
The boiler must be installed in rooms that comply with all local, state and
federal codes and laws. Before commissioning the boiler verify exhaust
flue and terminations are properly sealed and secured.
•
Adequate combustion air and ventilation is required for safe and
proper installation of the boiler, regardless whether the combustion air
is taken from the outside (Direct Vent, sealed combustion) or inside
(room air for combustion).
a
a
WARNING: Insufficient ventilation of the boiler room can
lead to high air temperatures and lead to risk of personal
injury or death from flue gas poisoning!
•
Make sure that intake and exhaust openings are sufficiently sized and no
reduction or closure of openings takes place. If these are not provided, do
not operate the boiler (see section “4.7.2 Connecting flue gas systems”).
•
The heating units cannot be installed outdoors. NEVER place this
appliance in a location that would subject it to temperatures at or near
freezing or temperature that exceed 120°F (49°C) while in operation.
Failure to properly locate this unit can result in premature failure.
•
This appliance must be installed in a location so that any water
leaking from the unit or piping connections or relief valve openings
will not cause damage to the area surrounding the unit or any lower
floors in the structure. When such locations cannot be avoided, it
is recommended that a suitable drain pan, adequately drained, be
installed under the boiler. The pan must not restrict combustion air flow.
•
When installed in a room with thin flooring, resonating noises may
occur. Isolate the boiler from direct contact with the floor to minimize
noise transmission.
•
Do not allow excessive dust to collect on the appliance.
a
a
WARNING: If the information in these instructions is not
followed exactly, a fire or explosion may result causing
property damage, personal injury or death.
•
Do not store or use gasoline or other flammable vapors and liquids in
the proximity of this or any other appliance.
•
Installation and service must be performed by a qualified installer,
service agency or the gas supplier.
•
Please consider the space needed for accessibility to safety and
control devices and for performing maintenance operations.
The recommended clearance for ease of installation and service are
illustrated in the following picture:
Fig. 9 Recommended minimum clearances for installation and
servicing (dimension in inches [mm])
2” (50.8 mm) clearance from combustibles is permitted, but respect the
clearance in Fig. 9 for serviceability”. The boiler can be installed on a
combustible (wood) floor excluding carpets.
NOTICE: This device is equipped with a freeze protection
function. For further information see section “5.8 Setting
frost protection”.
20” (500mm)
20” (500mm)
40” (1000mm)
2” (50mm)
4” (100mm)
4” (100mm)
Содержание Buderus SSB255
Страница 66: ...6720818454 2016 02 US SSB 66 Spare parts Notes ...
Страница 67: ...SSB 6720818454 2016 02 US Spare parts 67 Notes ...