10
2005 Boreal Geothermal Inc.
www.boreal-geothermal.com
Horizontal Trench Requirements
The ACDX heat pump requires one groundcoil or "loop"
per nominal ton of capacity.
Trenching for the ACDX heat pump can be best accom-
plished with a tracked excavator equipped with a 44” to 48”
bucket. If a wider bucket is available and you can afford the
extra cost, the trenches could be wider for improved perform-
ance.
The object, of course, is to allow the copper loops to
contact earth which has not been influenced by the prox-
imity of another loop.
The trenches are dug from 5 to 6 ft.
deep to a total length of 180'. Each of the ACDX loops is
350' long and when laid in the form of a U down each side of
the trench the turn at the end will occur at 175' allowing for a
small degree of error by the excavator operator. Take special
care that the bottom of the trench is kept as smooth as possi-
ble to reduce the chance of pinching or crushing the copper
tubing when backfilling the trench. If rocky conditions are
encountered it is recommended that the bottom of the trench,
especially the corners where the pipe will lay, be covered by
hand with limestone tailings, or some other heavy dense ma-
terial t provide a relatively smooth resting place for the cop-
per pipe. Unlike plastic pipe, the copper tubing will stay
where you put it when unrolled rather than arguing with you,
as plastic does, on a cool day. Once the pipe has been un-
rolled and placed, backfilling by hand to a depth of 4-6" with
fill as described above will ensure that the pipe is protected
from falling rock etc. during the machine backfilling proce-
dure.
Other excavating devices such as a ditch-witch (chain
digger) or a regular back-hoe can be used if ground conditions
permit however you will have to dig a U shaped trench with
spacing 5 ft. to 10 ft.. We have found that the greater speed
of the tracked excavator in most soil conditions and the fact
that you only have to dig one trench (which is excellent width
for a man to work in) more than compensates for it's extra
rental or operational costs.
An alternative technique for burying the underground cop-
per tubing would be to dig a large shallow pit with a bull-
dozer. This pit would have to be large enough to accommo-
date all the loops required in the system. The copper tubes
should have a spacing of at least 6 ft. minimum. A wider
spacing would lead to slightly greater efficiency.
Entering dwelling
The copper ground loops must enter the dwelling at some
location typically through the concrete foundation just above
the poured floor. An alternate method would be to run the
pipe (insulated) up the outside wall making a 90 degree turn
above ground and entering the dwelling between the floor
joists just below the first floor. These pipes should be insu-
lated with a minimum of 3/4" of closed cell weatherproof
insulation. There will be two 1/2" OD copper tubes for each
nominal ton of capacity of the heat pump being installed. For
example a 3-ton unit would have 3 groundloops and thus 6
ends to go through the concrete wall. We recommend that you
drill these holes to a diameter large enough to allow for the
insertion of a plastic sleeve, (see drawing ) and the tubing
with it's insulation jacket. Suitable measures must be taken to
seal the installation from water penetration before the trench
is backfilled.
Unrolling & placing the Tubing
Each 50' roll of tubing is taped both individually and to
the next roll in the group so that at any one time only 50' of
the 350' is free to unroll. This allows for easier unrolling and
prevents kinking the pipe. Observe how the taping is done so
that you know which side of the loop to start unrolling first.
To begin, unroll approximately 12' of copper tubing. Slide
two 6' lengths of armaflex closed cell insulation with wall
thickness of at least 1/2”over the end of the tubing and insert
it through the plastic sleeve of hole # 1 approximately 8" into
the basement. It is good practice to label this line
"loop 1 -
gas"
to identify it when interconnecting linesets inside the
building. Unroll the copper tubing down one corner of the
trench. When 175 ft of tubing has been laid out make your
turn and proceed back the other side of the trench to the foun-
dation of the building. Slide two 6' lengths of armaflex insula-
tion onto the tubing and insert the stub end through hole # 2 in
the wall to match the other end of the loop. Label this end of
the line
"loop 1 - liquid"
so that the complete loop can be
identified later. Manually backfill the loop with fill to a depth
of 4 to 6" for protection during the machine backfill process.
Duplicate the process described above applying labels to
identify the two ends of successive loops (loop 2,3,4 etc.)
until all required loops are in place.
Insulation placement near foundation
It is important to apply closed cell insulation to the copper
ground loops as they come within 12' of the building to pre-
vent the possible build up of ice near the foundation of the
home. Applying 1/2” wall closed cell waterproof insulation to
the tubing as described above will insure that very little heat
is absorbed from the ground near the basement wall thus
avoiding possible frost damage to the structure.
Pressure testing linesets
Using the 1/4" schrader valve supplied on each loop the
installer can again check the pressure on each lineset with his
refrigeration gauge set before releasing the pressure and cut-
ting the loop stubs coming into the basement to the proper
lengths.
Содержание ACDX-45
Страница 11: ...11 2005 Boreal Geothermal Inc www boreal geothermal com BOREAL ACDX Horizontal Trench Design ...
Страница 13: ...13 2005 Boreal Geothermal Inc www boreal geothermal com BOREAL Horizontal ACDX Heat Pump System Plan View ...
Страница 36: ...36 2005 Boreal Geothermal Inc www boreal geothermal com ...