8
Step 3:
Place the gear box mount over the end of the impeller shaft and secure the gear box with the four
bolts as shown in
Figure 3
.
Figure 3
Key
Step 4:
Remove the tape holding the key to the impeller shaft.
Align the key with the groove in the gear box as you lower the gear
box onto the shaft. Use the 4 bolts to bolt the gear box to the gear box
mount shown in
Figure 4a
.
Lift the impeller shaft on the inside of the kettle and tighten the nuts
above the gear box.
(Figure 4b)
Step 5:
Place the star end of the gearbox adapter into the gear box as shown in
Figure 5
.
Align the motor shaft with the gear box adapter shown in
Figure 6
.
Figure 4a
Figure 5
Step 7:
Using the nuts and bolts provided, secure the gear box to the motor.
Gearbox Adapter
Figure 6
Figure 4b