382506_A_HI
12
SWING ARM BUSHING REPLACEMENT CONTINUED
Maintenance
6. Place new bushings in swing arms. Use 1/2” pin or shoulder bolt to position the new bushing into the swing arm.
Use a hammer to gently tap on the pin/shoulder bolt to drive the new bushing into the swing arm. Remove the 1/2”
pin or shoulder bolt.
7. Repeat steps 5 & 6 on the second swing arm.
8. Reverse steps 1-4. Reattach the swing arms, then reattach the tine plate. Proceed to reattach the swing arm
support bar. Finally, reconnect the link lift to the swing arm support bar.
9. Tighten all joints. Use an impact wrench with correct sockets to ensure the all joints are secure before operation.
Ensure hardware orientation is the same as before disassembly.
Figure F
TINE PLATE REPLACEMENT
1. Disconnect the link lift from swing arm support bar. Use an impact wrench fitted with a 3/4” socket to remove the
1/2” bolt (see Figure A, circled in yellow). Set hardware aside to be reattached later.
2. Detach the swing arm support bar. Use an impact wrench fitted with a 1/2” socket to remove the four 5/16” bolts
and associated hardware (see Figure A, circled in orange). Set hardware aside to be reattached later. Remove the
swing arm support bar. At this stage, your machine should appear as in Figure B.
3. Detach the tine plate. Use an impact wrench fitted with the 1/2” socket to remove the four bolts and associated
hardware that secure the tine plate (see Figure C). Set hardware aside to be reattached later. Using your hands,
maneuver the plate down off of the tines (see Figure D).
4. Attach new tine plate. Maneuver the new plate over the tines. Secure into place with original hardware from
Step 3.
5. Reverse Steps 1 & 2. Reattach swing arm support bar then reconnect the link lift to the swing arm support bar.
6. Tighten all joints. Use the impact wrench with correct sockets to ensure the all joints are secure before opera
-
tion. Ensure hardware orientation is the same as before disassembly.
NOT