Page 12 of 16
BA_2005_2_GB_D2
Replacement for BA_2005_1_GB_D2
7. Start-up
To fill the reservoir
To adjust the metered quantities
Initially set the adjustment spindles to 5, to obtain the maximum oil delivery.
Then, after the trail run has been completed, adjust to give the desired metered quantities.
If possible avoid settings close to 0, i.e. giving less than about 1/8 of the max. metered quantities (see Item
5. "Specification", for the max. metered quantities). Replace gasket an cover and secure with the screws.
To carry out the trial run
Turn the crank until blubble-free oil issues uniformly from the ends of the pipes at the lubrication points.
Connect the pipe ends tightly using the pipe couplings. The drive may then be switched on and lubrication
started.