Nail 2x4 joist headers and

floor joist to 4x4.

It is important that the floor be level and square. Square the floor as follows: before nailing the
flooring, measure the floor diagonally (corner to corner). Then measure the opposite corners.

These measurements will be the same if the floor is square.

2x4 Floor Joist
spaced 16" o.c.

2x4 Joist Header

4x4 Treated Runners

Flooring

Outside Measurement

2.

Cut 2x4-12' floor joist to 11'-9". Treated lumber may be thicker than 1-1/2". Take this into

account when cutting the length of floor joists. Shorten joist measurements if necessary to
obtain 12'-0" building width.

1.

Cut (2) two 2x4 joist headers to 16' - 0". Layout for 16" on center joist spacing. 'X' marks

where floor joist will be placed.

Material Description

12' x 16' shed

2x4 Joist Headers

2 pcs.

16'

2x4 Floor Joist

13 pcs.

12'

4x4 Treated Runners

8 pcs.

8'

Flooring 5/8" or 3/4"

6 pcs. 4x8

Screw Floor Nails

2 lb.

8d

Galv. Box Nails

2 lb.

16d

16' - 0"  Floor Length

12' - 0" Wide

Constructing Details for Deluxe Floor System

Deluxe floors include 4x4 runners, standard floors do not

Check local building codes in your area, the construction may have to change. For a concrete slab,

install sill sealer as a moisture barrier between the concrete and the wall plates. Foam sill sealer can
be purchased at home centers  in rolls 3-1/2" or wider.

Содержание the Riviera

Страница 1: ...ive Greenville PA 16125 724 646 3775 This manual is copyrighted Under the copyright laws this manual may not be copied in whole or in part without consent from Reynolds Building Systems Inc Copyright...

Страница 2: ...ke the shipping pallet will be used for wall bracing The OSB sheathing will be used for roof sheathing Unpack the material from the pallet then disassemble the pallet The pallet is secured together wi...

Страница 3: ...ts Shorten joist measurements if necessary to obtain 12 0 building width 1 Cut 2 two 2x4 joist headers to 16 0 Layout for 16 on center joist spacing X marks where floor joist will be placed Material D...

Страница 4: ...ils per gusset 4 Install a 2x4 84 collar tie between the 2x4 boards Insure collar tie is parallel with edge of work surface see below Hold collar tie from moving with 2x4 blocks Install 12 x24 gussets...

Страница 5: ...ollar tie in place in Step 1 3 Place 2 two 66 long 2x4 truss members at the top of the truss jig 4 Install the gable plate assembled above to the truss legs with 2 1 2 wood screws see detail B Install...

Страница 6: ...top of the gable frame and gable studs Use 8d galv nails along the bottom edge 2 Install 55 1 2 wall studs red ends between the top and bottom plates Assemble wall frames with 10d sinkers two 2 nails...

Страница 7: ...wall frame Install the first full width siding panel with the LAP edge extending 3 1 2 past the wall frame Work from left to right The siding will extend 3 4 below the bottom plate Use 8d galv nails...

Страница 8: ...siding panel with the LAP edge extending 3 1 2 past the wall frame Work from right to left The siding will extend 3 4 below the bottom plate Use 8d galv nails spaced 12 apart Step 7 Install Siding on...

Страница 9: ...studs of the wall panel The left end will be flush edge of short stud The right end will extend beyond long stud by 1 1 2 to receive header support Siding will extend 3 4 below 2x4 plate Use 10d sink...

Страница 10: ...p and bottom wall plates 4 Install 74 1 2 long wall stud so that edge of siding is center of stud Front Wall Panel w Siding 66 1 2 Long 2x4 Plate 72 Long 2x4 Plate 2x4 Stud w Header Support 2x4 Stud w...

Страница 11: ...e pre built 59 1 2 door header between the front wall panels Nail through the wall stud on the larger panel into the end of the header Nail through the top wall plate that extends over the door header...

Страница 12: ...alv nails Siding Shim 4 Install a 46 1 2 long 2x6 on the right sidewall 5 Install 2nd 26 1 2 filler flush with the angle part of the front wall The filler will be 3 4 below top of the wall frame 6 Cut...

Страница 13: ...with bottom of 2x6 sidewall plate The filler should be 3 4 below the top of the wall frame Nail with 10d sinkers 2 Install a 52 1 4 long 1x4 trim board against the filler board and flush with the top...

Страница 14: ...ame when marking the location of the first truss Continue 24 spacing to front wall Important When marking the opposite wall place the X mark on the same side of the line so your trusses are parallel w...

Страница 15: ...at the 49 mark and flush with rear gable siding Insure sheathing meets the center of the truss at the break Use 7d sinkers spaced 12 apart The top row of roof sheathing will be about 1 below the ridg...

Страница 16: ...of the overhang This panel will slide in the gap between the filler board and 1x4 trim and rest on the 2x6 tie plate Use 6d glav nails 1 Install 1 one 96 long 2x4s against the siding and under roof s...

Страница 17: ...s 3 Install a 52 long x 2 1 2 wide board with the angle end at the peak of the roof 4 Install a 45 long x 2 1 2 wide board 5 Repeat steps 1 4 for opposite side 1x6 Trim Board Step 18 Install Gable Tri...

Страница 18: ...with the bottom edge of the siding Tack these boards with a couple nails you may want to adjust the trim later when you install the doors Use 8d galv nails 2 Install shingles according to the instruct...

Страница 19: ...in or out to make the door spacing equal 5 Install hinges to trim with 2 screws OSB Shim 1 Lay the left door with the trim facing up The siding on the left door extends past the door trim See detail...

Страница 20: ...Truss Hangers 6 ea 5 Door Hinges 1 ea 4 5 Door Latch 2 ea 6 Barrel Bolts 6 ea 1x4 Metal Plates 1 Bottle Glue and Bay of Screws 18 Truss Rafters 2x4 96 7 Collar Ties 2x4 84 6 Wall Studs 2x4 74 1 2 4 Wa...

Отзывы: