EN / CZone® Contact 6 PLUS User & Installation Manual
12
FIT THE COVER
Cover Installed
1. Slide the cable gland up the output wires ensuring it is correctly seated.
2. Firmly push the top cover on to the Contact 6 PLUS until you hear it click into pace on each side.
3. Ensure the cable gland is still correctly in place.
4.
Install circuit labels if you have purchased a label sheet.
WARNING!
The Contact 6 PLUS is only ignition protected with the cover correctly installed.
INITIAL POWER UP
Standalone Installation
1. Power up the system.
2. Check that the Network Status LED lights up.
3. Turn the switch/circuit breaker on supplying power to the input stud (if fitted), system will flash all outputs for a
short time while booting.
4. To toggle a circuit to momentary switching, press and hold the power button and the button for that circuit
together on the CZone Waterproof Keypad for 5 seconds.
5. Test all circuits for ON/OFF functionality.
6. Check the circuit status LED’s for each individual circuit. Refer to LED codes to diagnose any faults which
need to be rectified.
Networked Installation
1. Power up the NMEA2000 Network, system will flash all outputs for a short time while booting.
2. Check that the Network Status LED lights up. It may also be flashing if other devices are on the network and
transmitting data.
3. Turn the switch/circuit breaker on supplying power to the input stud (if fitted).
4. Check the software version on the Contact 6 PLUS with the CZone Configuration Tool and update if
necessary.
5. Write the configuration file to the network (Refer to the CZone Configuration Tool Instructions for details on
how to write a CZone configuration file).
6. Test all outputs for correctly configured functionality.
7. Check the circuit status LED’s for each individual circuit. Refer to LED codes to diagnose any faults which
need to be rectified.