Once the
Pre-fabricated
wall has been built
or
the
opening for the
Masonry Wall
has been made-
proceed with finishing the wall.
Depending on the wall medium, plasterboard or patch
up, skim and decorate the wall.
Once the decoration is complete proceed with
installing the
Surround
and
Fire
.
See Pages 11-12
Diagram 11
Note: If the product is to be installed into the cavity of the wall, an open chimney or flue, it is important that the
cavity / chimney / flue is blocked off to prevent any up / down draughts and falling debris which could restrict and
alter the airflow of the product, which may cause the safety cut out system in the fan heater to operate.
The product should never be sealed into an opening with the use of silicones or adhesives as this can also alter the
airflow and hinder any future servicing of the product
It is essential to include a header / lintel at the required height to ensure the fire does not support the weight of
the finished wall. See Diagram 10.
Installation - Pre-fabricated Wall / Masonry Wall
continued…
Diagram 10,
shows the required opening size for a
Pre-fabricated Wall
or
Masonry Wall
.
Diagram 10
Opening Size Required (mm)
FIRE
D (mm)
1000 3SL
1015
1250 3SL