Commissioning
The major components of the bell
free
Digital system are fitted with high quality pluggable
screw terminal blocks. This enables all the connections to the system to be fully
completed, whilst easily isolating individual pieces of equipment during testing and
commissioning.
When powering up for the first time, it is highly recommended that only the most basic
system be connected. i.e. 1 BF apartment station, 1 door controller and panel, and 1 video
controller; the remaining equipment can be isolated by unplugging terminal blocks.
NB: Ensure the 1 door and video controller remain interconnected and that the „end of line‟
controller is terminated temporarily using the jumpers (see page 23).
Proceed to test the system by calling the apartment station from the door panel in the
usual way. Any problems can be resolved by rechecking wiring and connections, assisted
by the variou
s suggestions and tests in the section “Troubleshooting”. Once the basic
system is fully functioning, continue to reconnect and test the remaining equipment item by
item until completed.